Regular Village Board meetings are typically held at 7:00 p.m., the first three Tuesdays of each month in Council Chambers of Village Hall (room 201), 123 Madison St. When a Regular Meeting falls on a holiday, the meeting typically is held the following night. The Village Board also meets in special sessions from time to time. However, dates and times of Special Meetings can vary and may change.

File #: RES 23-271    Name:
Type: Resolution Status: Passed
In control: President and Board of Trustees
On agenda: 9/5/2023 Final action: 9/5/2023
Title: A Resolution Approving an Amendment to the Task Order for Professional Engineering Services with Edwin Hancock Engineering Co. for Design and Construction Engineering Services for Alley Improvements in 2023 to Change the Not to Exceed Amount from $281,312 to $304,480 and Authorizing its Execution
Attachments: 1. Resolution - AmendmentTaskOrder2024AlleyDesign.pdf, 2. Amendment TaskOrder 2024AlleyDesign - Hancock.pdf, 3. Attachment B - Scope for 2024 Green Alley Design.pdf, 4. TaskOrder Alley Design.pdf, 5. MasterAgreement forTaskOrders - Hancock.pdf

Submitted By                     

Bill McKenna, Village Engineer

 

Reviewed By

A.M. Zayyad, Deputy Village Manager

 

Agenda Item Title

Title

A Resolution Approving an Amendment to the Task Order for Professional Engineering Services with Edwin Hancock Engineering Co. for Design and Construction Engineering Services for Alley Improvements in 2023 to Change the Not to Exceed Amount from $281,312 to $304,480 and Authorizing its Execution 

End

Overview

Overview

The Village of Oak Park received a grant award of $500,000 from the Metropolitan Water Reclamation District (MWRD) for their Green Infrastructure Partnership Program for the construction of four (4) permeable alleys and Parking Lot 10 for construction in 2024. Edwin Hancock is currently designing the 2024 alleys. An amendment to the Task Order is needed in order for Hancock to design these additional permeable alleys.

End

 

Recommendation

Recommendation

Adopt the Resolution.

 

Background

The Village recently received notice of the award of a Metropolitan Water Reclamation District of Greater Chicago (MWRD) Green Infrastructure Program cost-sharing grant for the construction of four (4) green alleys in 2024. The MWRD grant program will fund approximately 40% of the construction cost of these alleys. Construction of the alleys is estimated to cost approximately $700,000, using approximately $280,000 in MWRD funds. Per the terms of the Intergovernmental Agreement with MWRD, the design of the alleys must be complete by the end of 2023, with construction occurring in 2024.  

 

Edwin Hancock Engineering Co. (Hancock) was already in the process of designing the 2024 Alley Improvement Project. Staff requested a proposal from Hancock to perform the engineering design and environmental reviews of these four (4) green alleys. The cost for this additional design work is $23,168. This Amendment to the Task Order with Hancock increases the amount of the Task Order from $281,312 to $304,480. There are available funds from savings in the 23-4 Alley Improvement Project, which is approximately $90,000 under budget, to cover these additional costs for design. 

 

Fiscal Impact

There is approximately $94,326 available in the Fiscal Year 2023 Main Capital Improvement Fund Budget in account # 3095-43780-101-570964 (Public Works - Engineering, Alley Improvements) from savings on the construction contract to cover the additional $23,168 needed for this additional design work. 

 

DEI Impact

The installation of green infrastructure helps mitigate the volume of water entering the Village’s combined sewer system and meets the goals of the Climate Ready Oak Park Plan.

 

Alternatives

The Board can delay action to gain additional information.

 

Previous Board Action

On March 20, 2023, the Village Board approved a Task Order for Professional Engineering Services with Edwin Hancock Engineering Co. for Design and Construction Engineering Services for Alley Improvements in 2023, in an amount not to exceed $281,312.

 

On September 19, 2022, the Village Board approved a Resolution Authorizing the Submission of a Metropolitan Water Reclamation District of Greater Chicago Green Infrastructure Partnership Program Application for the 2024 Green Alleys and Permeable Parking Lot 10 Project.  

 

On September 20, 2021, the Village Board approved a Three-Year Master Agreement with Edwin Hancock Engineering Co. for Professional Engineering Services with an Option to Renew the Agreement for up to Two Additional one-year periods.

 

Citizen Advisory Commission Action

N/A.

 

Anticipated Future Actions/Commitments

There is a separate item on tonight’s Village Board meeting agenda for an Intergovernmental Agreement by and between the Village of Oak Park and the Metropolitan Water Reclamation District of Greater Chicago for the Design, Construction, Operation, and Maintenance of the Green Alleys and Parking Lot 10 Project in Oak Park, Illinois.

 

Intergovernmental Cooperation Opportunities

The MWRD Green Infrastructure Program involves MWRD working with the Village of Oak Park to provide funding for green infrastructure projects.