A Resolution Approving Temporary Construction Easements at 805 North Lombard Avenue and 850 Clinton Avenue for the Resurfacing of Various Streets Project and Authorizing Execution of the Required Documents
..end
Introduction
overview
Temporary construction easements are necessary at 805 North Lombard Avenue and 850 Clinton Avenue in order to lower and replace private sidewalks to allow for replacing the public sidewalk corner ramps so they are compliant with the Americans with Disabilities Act requirements. This Resolution authorizes the Village to acquire the required easements and authorizes the Village Manager to execute the associated documents for obtaining these easements.
end
body
Recommended Action
Adopt the Resolution.
Prior Board Action
There is no prior board action associated with this item.
Background
The 26-2 Resurfacing of Various Streets Project includes upgrading corner sidewalk ramps at many locations so that they are compliant with the Americans with Disabilities Act’s (ADA) requirements. This work sometimes requires lowering the public sidewalk so that the ramps do not exceed the maximum slope of 1 inch per foot. At two locations, the work to lower the public sidewalk necessitates the lowering and replacing of the private sidewalk. The temporary construction easements allow for the Village to replace private property sidewalk at the new elevations so that the public sidewalk ramps can meet ADA requirements.
The Village has been working with the property owner to secure these easements. The easements are being donated to the Village at no cost but obligate the Village to remove, replace, and restore impacted private property sidewalks and landscaping. The estimated cost of this work is $2,140 and is being paid for as part of the previously approved Resurfacing of Various Streets Project.
Timing Considerations
Adoption at this time will allow for the project to advance on a s suitable timeline.
Financial Impact
These easements are being donated, and the work necessary to construct the replacement sidewalk areas is included in the cost of the previously approved Resurfacing of Various Streets project.
Operations Impact
This proposed item is a core service responsibility of the Public Works Department.
DEI Impact
There is no DEI impact associated with this item.
Community Input
There has been no community input given in relation to this item.
Staff Recommendation
Adopt the Resolution, which will allow for construction of this project to move forward on its desired schedule.
Advantages:
• Approval of the easement will allow for the construction project to continue.
Disadvantages:
• There are no disadvantages to this recommendation.
Alternatives
Alternative 1
The Board can delay action to gain additional information.
Advantages:
• Board Members would be presented with the additional information they requested.
Disadvantages:
• The timing of the eventual Board action will impact the desired implementation schedule.
Alternative 2
The Board can vote down the item.
Advantages:
• There are no advantages to this alternative.
Disadvantages:
• Needed improvements would not occur.
Anticipated Future Actions
There are no anticipated future actions in relation to this item.
Prepared By: Bill McKenna, Assistant Public Works Director/Village Engineer
Reviewed By: Rob Sproule, Public Works Director
Approved By: Kevin J. Jackson, Village Manager
Attachment(s):
1. Resolution
2. Temporary Easement 805 N. Lombard
3. Temporary Easement 850 Clinton