Regular Village Board meetings are typically held at 7:00 p.m., the first three Tuesdays of each month in Council Chambers of Village Hall (room 201), 123 Madison St. When a Regular Meeting falls on a holiday, the meeting typically is held the following night. The Village Board also meets in special sessions from time to time. However, dates and times of Special Meetings can vary and may change.

File #: RES 24-268    Name:
Type: Resolution Status: Passed
In control: President and Board of Trustees
On agenda: 8/27/2024 Final action: 8/27/2024
Title: A Resolution Approving an Independent Contractor Agreement with J. Graham, LLC. for the Viaduct Art Installation, in an Amount Not to Exceed $235,000 and Authorizing its Execution
Attachments: 1. Resolution - Agreement Graham Carraway OP Ave Viaduct Art.pdf, 2. Final Agreement Viaduct Art Graham Carraway.pdf, 3. Exhibit A - Proposed Viaduct Art Installation - Graham Carraway Reduced.pdf

Submitted By                     

Bill McKenna, Village Engineer/Assistant Public Works Director

 

Reviewed By

Erin E. Baynes, Assistant to the Village Manager

 

Agenda Item Title

Title

A Resolution Approving an Independent Contractor Agreement with J. Graham, LLC. for the Viaduct Art Installation, in an Amount Not to Exceed $235,000 and Authorizing its Execution   

End

Overview

Overview

As directed by the Village Board at the June 11, 2024 meeting, staff negotiated an agreement with Graham Carraway of J. Graham, LLC. for the fabrication, installation, and purchase of an art installation under the viaduct on Oak Park Avenue as part of the proposed Oak Park Avenue Streetscape project. The cost to fabricate and install the art is $235,000. The additional expense reflects costs for aluminum panels to wrap the corners of the viaduct along North and South Boulevard.  

End

 

Recommendation

Recommendation

Adopt the Resolution. 

 

Background

As directed by the Village Board at their June 11, 2024 meeting, staff negotiated an agreement with J. Graham, LLC. for the fabrication, installation, and purchasing of an art installation under the viaduct on Oak Park Avenue as part of the proposed Oak Park Avenue Streetscape project.  The original cost estimate for the installation was $200,000.  During negotiations, staff requested to use an aluminum panel system to wrap the mural around the corners of the viaduct on the North and South Blvd corners as opposed to painting the concrete wall. The additional expense for the aluminum panel system, including the cost to provide a contact bond, increased the total cost for the installation from the original estimate of $200,000 to $235,000.  

 

Pending approval of the agreement, Graham Carraway will start the design of the mural this summer. The design will be reviewed by the Oak Park Area Arts Council and staff before approval for installation. Following approval of the artwork, fabrication of the panel system will start in late 2024. Installation of the artwork is planned for fall 2025 during the streetscape project.     

 

Graham’s concept for the art installation under the viaduct goes beyond traditional sculpture; it is designed to be an interactive and immersive experience for the audience. Combining both fabricated elements and a mural component, his vision aims to invite individuals to actively participate in the artwork, thus transforming the installation into a dynamic and engaging space. By incorporating elements that allow individuals to insert themselves into the artwork, the artist hopes to foster a sense of ownership and connection among residents and visitors alike. The concept includes aluminum panels along the viaduct walls with illuminated archways fabricated into the panels. The archways would be lit by multiple colored LEDs that would be programmed to allow for changing colors.  The metal panels would also incorporate cutouts that allow decorative lighting to come through the panel and interact with the mural which will be painted on the aluminum panels.  The design of the mural would be in a similar style as the mural shown on page 5 of the artist’s proposal but incorporate local elements from the community.  The final design of the mural will be reviewed by the internal selection team which includes representatives from the OPAAC and Oak Park Art League.

 

Fiscal Impact

There are available funds in the Fiscal Year 2024 budget in the Capital Improvement Fund, Public Works - Engineering, Capital Improvements, External Support account no. 3095-43780-101-530667 to cover the $45,000 needed for the 2024 portion of the agreement. The proposed Fiscal Year 2025 Budget will include the additional $190,000 needed for this art installation as part of the Oak Park Avenue Streetscape Project’s cost in the Capital Improvement Fund, Public Works - Engineering, Capital Improvements, Streetscaping account no. 3095-43780-101-570959. 

 

DEI Impact

Public art allows for all residents and visitors to experience creative expression and positive interaction with the public space.

 

Alternatives

The Board can delay action to gain additional information.

 

Previous Board Action

At the Village Board meeting on June 11, 2024, the Village Board approved a Motion to Concur with the Recommendation of the Oak Park Area Arts Council to Enter an Independent Contractor Agreement with Graham Carraway for the Viaduct Art Installation and Direct Staff to Prepare the Necessary Agreement  

 

At the Village Board meeting on December 4, 2023, the Village Board approved the conceptual design, scope, and a $14.7 million budget for the Oak Park Avenue Streetscape and Utility Projects.

 

At the Village Board meeting on December 4, 2023, the Village Board approved a Professional Services Agreement with Terra Engineering, Ltd. for the Design of the Oak Park Avenue Streetscape and Utility Projects, in an amount not to exceed $998,577.

 

At the Village Board meeting on October 23, 2023, the Village Board had a presentation and discussion of the Oak Park Avenue Streetscape Project and the Oak Park Avenue Streetscape Steering Committee’s Recommended Conceptual Design and Alternatives.

 

At the Village Board meeting on September 5, 2023, the Village Board approved a Second Amendment to the Professional Services Agreement with Terra Engineering, Ltd. for the Design of the Oak Park Avenue Resurfacing, Utility, and Streetscape Projects to change the not to exceed amount from $1,010,958 to $1,214,548. 

 

At the Village Board meeting on March 6, 2023, the Village Board approved a Resolution Creating a Steering Committee for the Oak Park Avenue Streetscape Project and a Motion to Approve the Appointment of Members to the Steering Committee.

 

At the Village Board meeting on November 21, 2022, the Village Board approved an Amendment to the Professional Services Agreement with Terra Engineering, Ltd. for the Design of the Oak Park Avenue Resurfacing, Utility, and Streetscape Projects to change the not to exceed amount from $775,037 to $1,010,958.

 

At the Village Board meeting on September 16, 2019, the Village Board approved a Professional Services Agreement with Terra Engineering, Ltd. for the design of the Oak Park Avenue Resurfacing, Utility, and Streetscape Projects, in an amount not to exceed $775,037.

 

At the September 9, 2019, Special Meeting, the Village Board had a presentation and discussion on the design and construction of the Oak Park Avenue Resurfacing, Utility, and Streetscaping Projects. 

 

Citizen Advisory Commission Action

N/A.

 

Anticipated Future Actions/Commitments

N/A

 

Intergovernmental Cooperation Opportunities

N/A