Legislation Details

File #: RES 26-220    Name:
Type: Resolution Status: Passed
In control: President and Board of Trustees
On agenda: 6/9/2026 Final action: 6/9/2026
Title: A Resolution Approving a Contract with Visu-Sewer of Illinois, LLC for Project 26-10, 2026 Sewer Rehabilitation, in an Amount not to Exceed $350,000 and Authorizing its Execution
Attachments: 1. 1 - Resolution, 2. 2 - Contract and Bond, 3. 3- Visu Sewer Proposal, 4. 4- Bid Summary, 5. 5-Project location map

 

Title

title

A Resolution Approving a Contract with Visu-Sewer of Illinois, LLC for Project 26-10, 2026 Sewer Rehabilitation, in an Amount not to Exceed $350,000 and Authorizing its Execution                                                       

..end

 

Introduction

overview

The Village received five bids for Project 26-10, 2026 Sewer Rehabilitation. The low responsible bid was submitted by Visu-Sewer of Illinois, LLC in an amount of $175,821.25. The project as bid included the trenchless rehabilitation of 4 sewer segments at various locations within the Village. The low bid is under the budgeted amount, and staff recommends awarding the contract at the available budget amount of $350,000 to take full advantage of the competitive pricing that was offered. The additional funds will allow for the rehabilitation of an additional 4 sewer locations within the Village.                                          

end
body

Recommended Action

Adopt the Resolution.

Prior Board Action

There is no prior Board action associated with this item.

Background

The Village has a yearly sewer televising contract to clean and inspect its combined sewer system. The locations included in this project were found to need rehabilitation as part of this inspection process. When a sewer segment is found to be failing, one of the strategies used to repair it is sewer lining. Sewer lining is a process that installs a flexible epoxy-impregnated liner within the existing pipe and ‘cooks’ the liner using hot water or steam. This method of sewer repair avoids the expensive and disruptive digging process but is only suitable if the sewer is in good enough condition to install the liner and the existing sewer has adequate capacity. The service life of a lined sewer is anticipated to exceed 50 years.

Competitive bids were opened on May 21, 2026 for Project 26-10, 2026 Sewer Rehabilitation. Seven contractors downloaded the bid documents and five bids were received. The low responsible bid was submitted by Visu-Sewer of Illinois, LLC in an amount of $175,821.25. The project as bid included the trenchless rehabilitation of 4 sewer segments at various locations within the Village. Awarding the contract to the budgeted amount of $350,000 will allow for the rehabilitation of an additional 4 locations.

Timing Considerations

Adoption of the Resolution at this time will allow the contractor to complete construction in the desired timeframe to minimize disruption to nearby schools and complete the project by December 14, 2026.

Financial Impact

There is $350,000 budgeted for this project in the Water and Sewer Fund, Public Works - Sewer, Sewer Collection, Capital Improvements account no. 5040.43750.781.570707.

Operations Impact

There is no operating impact associated with this item. The item aligns with the Public Works Department’s core service delivery.

DEI Impact

There is no DEI impact associated with this item.

Community Input

There has been no community input given in relation to this item

Staff Recommendation

Adopt the Resolution.

Advantages:

                     This contract will allow for the procurement of needed services.

Disadvantages:

                     There are no disadvantages to this recommendation.

Alternatives

Alternative 1:

The Board can table the item for additional information or discussion

Advantages:

                     The Village Board would be provided with the requested information

Disadvantages:

                     The timing of the eventual Board action will impact the desired implementation schedule.

Alternative 2:

The Board can vote down the item.

Advantages:

                     This action may result in cost savings

Disadvantages:

                     Needed sewer rehabilitation will not occur

Anticipated Future Actions

There are no anticipated future actions in relation to this item.

Prepared By: Chris Welch, Assistant Village Engineer

Reviewed By: Rob Sproule, Public Works Director

Approved By: Kevin J. Jackson, Village Manager

Attachment(s):

1.                     Resolution

2.                     Contract and Bond

3.                     Proposal

4.                     Bid Summary

5.                     Project Location Map