Regular Village Board meetings are typically held at 7:00 p.m., the first three Tuesdays of each month in Council Chambers of Village Hall (room 201), 123 Madison St. When a Regular Meeting falls on a holiday, the meeting typically is held the following night. The Village Board also meets in special sessions from time to time. However, dates and times of Special Meetings can vary and may change.

File #: RES 17-591    Name:
Type: Resolution Status: Passed
In control: President and Board of Trustees
On agenda: 7/17/2017 Final action: 7/17/2017
Title: A Resolution Approving an Amendment to the Independent Contractor Agreement with H&H Electric Co. for Street Lighting & Traffic Signal Repairs in Amount Not to Exceed $33,500.00 in Fiscal Year 2017 and Authorizing its Execution
Attachments: 1. Resolution-H&H Electric, 2. Agreement Amendment-H&H Electric, 3. Attachement-H&H Electric Agreement, 4. Attachment-ISS_CERT_H&H Electric, 5. 2017 Emergency Street Light & Traffic Signal Repair RFB, 6. 2017 Emrgncy Street Lght & Trfc Cntrl Bid Tab

Submitted By                     

John P. Wielebnicki, Director of Public Works

 

Reviewed By

LKS

 

Agenda Item Title

Title

A Resolution Approving an Amendment to the Independent Contractor Agreement with H&H Electric Co. for Street Lighting & Traffic Signal Repairs in Amount Not to Exceed $33,500.00 in Fiscal Year 2017 and Authorizing its Execution

 

End

Overview

Overview

To avoid delays in making emergency repairs or to make street lighting rehabilitation/ improvements beyond the capacity of in-house staff, hourly rates from qualified contractors were requested from area contractors.  H & H Electric, Co. is the primary contractor in this area of work.  In early 2017, the Village entered into an agreement with this contractor and staff is requesting to amend the agreement to allow for additional repair work.

 

Body

Staff Recommendation

Approve the Resolution.

 

Fiscal Impact

The FY 2017 Public Works, Street Lighting Budget provides $55,000.00 for emergency repairs in the Street lighting and Traffic Signal General Contractual accounts no. 1001-43720-751-530660 ($45,000.00) and 1001-43720-752-530660 ($10,000.00).

 

The funds are split up between three contractors, H & H Electric, Co., Meade Inc., and Lyons Electric Co. Inc.

 

The current agreement with H&H Electric, Inc. is for $23,500.00 and it is proposed to be amended to $33,500.00.  Since the proposed amendment to the agreement with H&H Electric Co. is the only one of the three that exceeds the Village Manager’s spending authority, it is the only one that requires Village Board approval.

 

The cost for street lighting and traffic signal system repairs in 2017 will not exceed $55,000.00 in total from all contractors.  To date, $18,903.21 has been spent.

 

Background

The Department of Public Works, Street Lighting Division staff typically makes in-house repairs and upgrades to the street lighting and traffic signal systems.  When in-house staff is unavailable, or lacks the necessary equipment to perform emergency repairs or upgrades, an outside contractor is utilized to make the repairs or to do the work.  Typical examples of such repairs and improvements are:

 

1.                     Streetlight and/or traffic signal pole knockdowns due to vehicular accidents.

2.                     Underground electrical cable failures due to contractors hitting and breaking the lines while digging in the parkway.

3.                     Storm damage resulting in downed aerial lighting cables or damaged poles.

4.                     Traffic control cabinet failures due to accidents or electrical outages.

5.                     Running new underground electrical cable where overhead cable currently exists

 

The number of emergency repairs needed cannot be predicted, therefore, the amount spent for such services may vary from year to year.

 

The Street Lighting Division received three quotes for labor and equipment from area electrical contractors for emergency repairs in response for a Request for Prices dated December 29, 2016.  These quotes will also be used for street lighting system rehabilitation.

 

Public Works practice is to call out the contractor with the lowest pricing first.  If the preferred contractor is unavailable, the next available contractor who submitted the next most favorable pricing will be called, and so forth.

 

All three contractors are qualified to perform the work and have performed quality service for the Village in the past.  The total amount budgeted is $55,000.00 with the allocation of work depending on each contractor’s availability and specialty.

 

Alternatives

The Board can delay action to gain additional information.

 

Previous Board Action

The Board approved similar action in previous years.

 

Citizen Advisory Commission Action

N/A.

 

Anticipated Future Actions/Commitments

It is anticipated that the Department of Public Works will be bringing these agreements to the Village Board annually.

 

Intergovernmental Cooperation Opportunities

The Village is the only Oak Park agency within the community that utilizes these services regularly.

 

Performance Management (MAP) Alignment

This work is in alignment with the Governance Priority established for the Department of Public Works for Maintenance and Service Programs.