Legislation Details

File #: RES 15-488    Name:
Type: Resolution Status: Passed
In control: President and Board of Trustees
On agenda: 11/16/2015 Final action: 11/16/2015
Title: A Resolution Authorizing a Change Order for the Professional Services Agreement with Edwin Hancock Engineering Co. for the 2015 Alley Improvements Project for an Additional $11,068
Attachments: 1. 11-16-15_Resolution_ChangeOrderHancockAlleys.pdf, 2. 2015AlleyEngineeringAgreement.pdf, 3. 2015AlleyEngineeringFinalCostSummary.pdf

Submitted By                     

Bill McKenna, Village Engineer

 

Reviewed By

LKS

 

Agenda Item Title

Title

A Resolution Authorizing a Change Order for the Professional Services Agreement with Edwin Hancock Engineering Co. for the 2015 Alley Improvements Project for an Additional $11,068

 

End

Overview

Overview

The Village of Oak Park has an agreement with Edwin Hancock Co.to provide design and construction engineering services for the 2015 alley improvements.  Additions to the engineering contract scope for environmental testing and construction staking have resulted in a contract increase of $11,068 over the original contract amount of $248,600. 

 

Body

Staff Recommendation

Approval.

 

Fiscal Impact

There are sufficient available funds in the FY2015 Capital Improvement fund for Alley Improvements, account no. 3095-43780-101-570964 to cover the $11,068 cost for the change order to this contract. The two alley improvement construction contracts are complete and are approximately $50,426 under the awarded contract amounts resulting in approximately $100,000 in remaining funds in the FY2015 alley improvement budget.   

 

Background

Edwin Hancock Engineering was awarded a contract in November of 2014 to design and manage the 2015 alley improvements for the Village of Oak Park.   The Engineering Division added additional scope to this contract to perform environmental soil testing to identify locations with contaminated soils in order to have results in time for an early construction contract bidding and also added scope to have Edwin Hancock Engineering perform construction layout to save the Village costs from the contractor doing this work.  The Engineering Division also reduced their contract scope for materials testing.  The net result of the various changes orders to the contract scope resulted in a contract cost increase of $11,068. 

 

Edwin Hancock Engineering has done an excellent job overseeing the two alley improvement projects.  They were able to add two additional alley locations into the project and keep the construction costs under budget.   The costs savings from the construction contracts will be used to fund the change order.  

 

Alternatives

There are no proposed alternatives with this change order request as scope changes were approved at various time during the design and management of the project.

 

Previous Board Action

On November 3, 2014 the Village Board authorized a professional service agreement with Edwin Hancock Engineering Co. for Professional Engineering Services for Design and Construction Engineering of the 2015 Alley Improvements in an amount not to exceed $248,600. 

 

On September 8, 2015 the Village Board authorizing a Renewal Agreement with Edwin Hancock Engineering Co. for Professional Engineering Services for Design and Construction Engineering of the 2016 Alley Improvements in an amount not to exceed $231,600. 

 

Citizen Advisory Commission Action

N/A.

 

Anticipated Future Actions/Commitments

None at this time.

 

Intergovernmental Cooperation Opportunities

None at this time.

 

Performance Management (MAP) Alignment

This work is in alignment with the Governance Priority for the Department of Public Works for Infrastructure/Capital Programs.