Regular Village Board meetings are typically held at 7:00 p.m., the first three Tuesdays of each month in Council Chambers of Village Hall (room 201), 123 Madison St. When a Regular Meeting falls on a holiday, the meeting typically is held the following night. The Village Board also meets in special sessions from time to time. However, dates and times of Special Meetings can vary and may change.

File #: RES 24-338    Name:
Type: Resolution Status: Consent Agenda
In control: President and Board of Trustees
On agenda: 11/19/2024 Final action:
Title: A Resolution Approving an Amendment to the Task Order for Professional Engineering Services with V3 Companies, Ltd. for Construction Engineering Services for the 24-7 Austin Boulevard Sewer Improvements Project to Change the not to Exceed Amount from $76,493 to $95,493 and Authorizing its Execution
Attachments: 1. Resolution - AmendmentAustinSewerCE - V3.pdf, 2. Amendment TaskOrder AustinSewer Engineering - V3.pdf, 3. Attachment B - RequestAmendment.pdf, 4. TaskOrder Austin Sewer Eng - V3.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Submitted By                     

Bill McKenna, Assistant Public Works Director/Village Engineer

 

Reviewed By

A.M. Zayyad, Deputy Village Manager

 

Agenda Item Title

Title

A Resolution Approving an Amendment to the Task Order for Professional Engineering Services with V3 Companies, Ltd. for Construction Engineering Services for the 24-7 Austin Boulevard Sewer Improvements Project to Change the not to Exceed Amount from $76,493 to $95,493 and Authorizing its Execution 

End

Overview

Overview

V3 Companies has been overseeing the construction of the Austin Boulevard Sewer Improvement Project being constructed by Millennium Contracting. The construction project experienced delays primarily associated with permitting requirements from Union Pacific Railroad and by Illinois Department of Transportation which resulted in V3 having to oversee the project beyond the anticipated hours in their original Task Order and proposal. 

End

 

Recommendation

Recommendation

Adopt the Resolution.

 

Background

V3 Companies has been overseeing the construction of the Austin Boulevard Sewer Improvement Project being constructed by Millennium Contracting.  The construction project experienced delays primarily associated with permitting requirements from Union Pacific Railroad and by Illinois Department of Transportation (IDOT) which resulted in V3 having to oversee the project beyond the anticipated hours in their original Task Order and proposal. 

 

The Union Pacific (UP) permitting delays were associated with UP issuing approvals for the contractor to start work for inspecting and repairing the sewer and replacing the roadway under the UP viaduct between North and South Boulevards.  The IDOT permitting delays were associated with the IDOT permit for traffic control associated with the emergency water supply disconnection at the Roosevelt Road and Austin Boulevard intersection.  These delays were outside of V3 or the contractor’s ability to control but extended the duration of the project.   Overall construction of the project was completed under the awarded dollar amount and there are savings from the construction contract that will cover the costs associated with this amendment.   

 

Fiscal Impact

There is $2,687,414 available for this amendment in the Fiscal Year 2024 Budget in the Water & Sewer Fund, Public Works - Sewer, Sewer Collection, Capital Improvements account no. 5040.43750.781.570707.

 

DEI Impact

N/A.

 

Alternatives

The alternative to this recommendation could be to delay action to gain additional information.

 

Previous Board Action

On March 5, 2024, the Village Board approved a Task Order for Professional Engineering Services with V3 Companies, Ltd. for Construction Engineering Services for the 24-7 Austin Boulevard Sewer Improvements Project in an amount not to exceed $76,493.

 

On September 20, 2021, the Village Board approved a Three-Year Master Agreement with V3 Companies, Ltd. for Professional Engineering Services with an Option to Renew the Agreement for up to Two Additional One Year Periods.

 

Citizen Advisory Commission Action

N/A.

 

Anticipated Future Actions/Commitments

None at this time.

 

Intergovernmental Cooperation Opportunities

N/A.