Regular Village Board meetings are typically held at 7:00 p.m., the first three Tuesdays of each month in Council Chambers of Village Hall (room 201), 123 Madison St. When a Regular Meeting falls on a holiday, the meeting typically is held the following night. The Village Board also meets in special sessions from time to time. However, dates and times of Special Meetings can vary and may change.

File #: RES 25-268    Name:
Type: Resolution Status: Consent Agenda
In control: President and Board of Trustees
On agenda: 10/14/2025 Final action:
Title: A Resolution Approving the Purchase of Temporary Construction and Permanent Sidewalk Easements on Oak Park Avenue and Authorizing Execution of the Required Documents
Attachments: 1. Resolution 25-268
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title
title
A Resolution Approving the Purchase of Temporary Construction and Permanent Sidewalk Easements on Oak Park Avenue and Authorizing Execution of the Required Documents
end

Introduction
overview
Sidewalk easements are necessary to construct sidewalk and alley improvements in the Hemingway Business District as the property line extends into the sidewalk or alley areas at certain locations. There are five properties where easements are required and some of the property owners have requested compensation. This Resolution authorizes the Village to acquire the required easements and authorizes the Village Manager to execute the associated documents for obtaining these easements.
end
body
Recommended Action
Adopt the Resolution.
Prior Board Action
There is no prior Board action associated with this item.
Background
The proposed Oak Park Avenue streetscape project includes replacing the sidewalk up to the building face along Oak Park Avenue in the Hemingway Business District. On the west side of Oak Park Avenue, from North Boulevard to Lake Street, the buildings are set back approximately four feet from the property line. There are no existing sidewalk easements recorded against these five private properties.
The Village has been working with the property owners to acquire sidewalk easements so that the Village can replace the sidewalk on private property. The Village has been requesting to obtain permanent easements to allow for the construction of the project and to have a permanent easement in place, which allows the public to use the sidewalk and for the Village to maintain the sidewalk. The Village has been requesting that property owners donate the sidewalk easements since the Village will be replacing the sidewalks at no cost to the property owners. To date, at least two of the properties have agreed to donate either a temporary construction easement or permanent sidewalk easements.
This Resolution approves the acquisition ...

Click here for full text