The Public Works Department Water & Sewer Division, on occasion, require the assistance of an outside water and sewer contractor to make a repair when in-house staff are unable to make repairs due to competing priorities or complexity of the required repair. Due to a complex repair on February 4, 2026, the Village had to contract a repair with Cerniglia Co. that utilized more than half of the existing contract amount available for the remainder of the year. Public Works staff recommend increasing the not to exceed amount to $75,000 because on average the department has contracted repairs annually that total between $70,000 and $80,000 with Cerniglia Co.
end
body
Recommended Action
Approve the Resolution.
Prior Board Action
In the past, the Village Board has approved funding for emergency water and sewer repair contractor agreements.
Background
The Public Works Department Water & Sewer Division typically makes repairs to the water distribution and sewer collection systems utilizing in-house staff and expertise. On occasions when in-house staff is unable to make repairs, for instance when crews are performing snow removal operations, lack the necessary equipment to perform such repairs, or multiple repairs are required simultaneously, an outside water and sewer contractor is called in to make the repair.
On February 4, 2026, Water & Sewer Division staff were made aware of a 15" sewer main that was hit by an IDOT contractor following an inaccurate fulfillment of a JULIE request. The urgent nature of, complexity, and depth at which the repair was needed required staff to utilize the existing contract with Cerniglia Co. to complete. This repair alone used...