Title: An Ordinance Granting an Extension of Time to Complete Construction of the Planned Development at 715-717 South Boulevard (Residences of South Boulevard) to May 31, 2024
Attachments: 1. Ordinance, 2. ORD 23-29, 3. ORD 22-53, 4. ORD 22-15, 5. ORD 21-28, 6. ORD 20-22, 7. ORD 18-398, 8. ORD 17-174- Residence of So. Blvd., 9. Art Request 10.24.23.pdf
Submitted By
Ahmad M. Zayyad, Deputy Village Manager / Interim Director of Development Customer Services

Reviewed By
LKS

Agenda Item Title
Title
An Ordinance Granting an Extension of Time to Complete Construction of the Planned Development at 715-717 South Boulevard (Residences of South Boulevard) to May 31, 2024

End
Overview
Overview
717 South Boulevard, LLC is requesting approval of an extension of its planned development ordinance deadline to allow additional time to finish construction of the multi-unit residential condominium building constructed at 715-717 South Boulevard. This is the sixth request to extend the development's timeline.

End
Recommendation
Recommendation
Adopt the Ordinance to allow an extension of time for the completion of construction. The applicant is requesting an additional six (6) month extension from November 30, 2023 to May 31, 2024, as stated in the attached request letter. Staff supports the extension.

Fiscal Impact
N/A.

Background
The Zoning Ordinance at the time of Planned Development approval stated in Article 14; Section 14.5(G)2&3 that an approval of a planned development permit by the Board of Trustees shall be null and void if the recipient does not file an application for a building permit for the proposed development within nine months after the date of adoption of the Zoning Ordinance approving the development permit; commence construction within eighteen (18) months, and complete the project within thirty-six (36) months. Article 14 of the Zoning Ordinance allows the Village Board to grant an extension of time, provided the applicant shows good cause in writing.

The Applicant has indicated that additional time is necessary, as stated in the attached email dated October 24, 2023, attached hereto. Ordinance Number 17-174, approved by the Village Board on March 6, 2017, authorized the construction of a multiple-unit residential development with private parking. As of this writing, the development of th...