Submitted By
Bill McKenna, Village Engineer
Reviewed By
A.M. Zayyad
Agenda Item Title
Title
A Resolution Approving a Task Order for Professional Engineering Services with Edwin Hancock Engineering Co. for Design Engineering Services for the 2023 Division Street Resurfacing Project in an Amount Not To Exceed $264,942 and Authorizing its Execution
End
Overview
Overview
The Engineering Division requested a proposal from Edwin Hancock Engineering Co. to provide design engineering for the 2023 Division Street Resurfacing project. Edwin Hancock has previously designed street resurfacing projects in the Village and is most qualified to perform these services. Division Street is planned for resurfacing in 2023 using REBUILD Illinois funds. Design work for the project would start this spring in order to bid the project in the late fall or early winter for the most advantageous pricing. Construction of the resurfacing would start in the late spring of 2023 following a separate locally funded water and sewer project on Division.
End
Recommendation
Recommendation
Approve the Resolution.
Fiscal Impact
The proposed FY2022 Budget includes $350,000 for the design engineering work for this project in the Capital Improvement Fund, Public Works - Engineering, Capital Improvements, Project Engineering account no. 3095-43780-101-570706.
The future construction project for the resurfacing of Division Street in 2023 will utilize REBUILD Illinois funds.
Background
The Engineering Division requested a proposal from Edwin Hancock Engineering to provide design engineering services for the Division Street Resurfacing project. Edwin Hancock has previously completed design engineering for similar street resurfacing projects using REBUILD Illinois funds and has done an excellent job at a competitive rate and is best qualified to perform this work. Edwin Hancock is one of the four engineering consulting firms with a Master Agreement approved by the Village Board for ...