Regular Village Board meetings are typically held at 7:00 p.m., the first three Tuesdays of each month in Council Chambers of Village Hall (room 201), 123 Madison St. When a Regular Meeting falls on a holiday, the meeting typically is held the following night. The Village Board also meets in special sessions from time to time. However, dates and times of Special Meetings can vary and may change.

File #: RES 17-673    Name:
Type: Resolution Status: Passed
In control: President and Board of Trustees
On agenda: 11/6/2017 Final action: 11/6/2017
Title: A Resolution Approving an Amendment to the Professional Services Agreement with Hampton, Lenzini and Renwick, Inc., for Construction Engineering Services for Project 17-2, Resurfacing of Various Streets, for an additional $32,144 and Authorizing its Execution
Attachments: 1. 11-06-17_Resolution-17-2 Engineering change order.pdf, 2. 11-06-17-Amendment_HLR_Resurfacing Egnineering 17-2.pdf, 3. 11-06-17_17-2HLR_OriginalContract.pdf, 4. 11-06-17_HLR Oak Park Extra.pdf
Submitted By
Bill McKenna, Village Engineer

Reviewed By
LKS

Agenda Item Title
Title
A Resolution Approving an Amendment to the Professional Services Agreement with Hampton, Lenzini and Renwick, Inc., for Construction Engineering Services for Project 17-2, Resurfacing of Various Streets, for an additional $32,144 and Authorizing its Execution

End
Overview
Overview
The original scope of the contract did not include construction engineering for the Westgate and North Boulevard street resurfacing related to the Emerson development. The work to provide this additional engineering is $32,144 and adjusts the contract amount to $152,734.69.

Body
Staff Recommendation
Approve the Resolution

Fiscal Impact
The FY2017 Budget includes $1,681,000 in the Capital Improvement Fund, Public Work - Engineering, Streetscaping, for the Colt Site Streetscaping account no. 3095-43780-101-570959 for the construction engineering of the streetscaping and roadway work for resurfacing North Boulevard and Westgate which will be used to fund this change order.

Background
The RDA for the Emerson Development does not include the street resurfacing of Westgate Street west of the development's frontage nor of North Boulevard from Harlem Avenue to Marion Street. The roadway needs to be resurfaced based on condition and from trenching done as part of water and sewer main improvements and from ComEd public facility relocation work.

On October 2, 2017 a change order was approved with the contractor, Crowley Sheppard to perform this work. Hampton, Lenzini and Renwick (HLR) has the contract to perform the construction engineering services for this street resurfacing contract with Crowley Sheppard and their oversight is needed to complete this work and to coordinae with the adjacent development.

Alternatives
The alternative to this recommendation could be to delay action to gain additional information.

Previous Board Action
On July 17, 2017 the Village Board approved a Resolution Appr...

Click here for full text