Regular Village Board meetings are typically held at 7:00 p.m., the first three Tuesdays of each month in Council Chambers of Village Hall (room 201), 123 Madison St. When a Regular Meeting falls on a holiday, the meeting typically is held the following night. The Village Board also meets in special sessions from time to time. However, dates and times of Special Meetings can vary and may change.

File #: RES 25-246    Name:
Type: Resolution Status: Consent Agenda
In control: President and Board of Trustees
On agenda: 8/5/2025 Final action:
Title: A Resolution Approving an Independent Contractor Agreement with Garland/DBS, Inc. for PWC Floor Sealing through Omnia Partners Master Intergovernmental Cooperative Purchasing Agreement (Micpa) #PW1925 in an Amount not to Exceed $126,192.00, Authorizing its Execution and Waiving the Village's Bid Process for the Agreement
Attachments: 1. 1 - Resolution - 2025 PWC Floor Sealing, 2. 2 - Independent Contractor Agreement - 2025 PWC Floor Sealing, 3. 3 - Supporting Contract Documents - PWC Floor Sealing
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title
title
A Resolution Approving an Independent Contractor Agreement with Garland/DBS, Inc. for PWC Floor Sealing through Omnia Partners Master Intergovernmental Cooperative Purchasing Agreement (Micpa) #PW1925 in an Amount not to Exceed $126,192.00, Authorizing its Execution and Waiving the Village's Bid Process for the Agreement
end

Introduction
overview
This project entails the installation of a traffic coating membrane in designated sections of the first-floor vehicle storage area at the Public Works Center (PWC). The coating is necessary to mitigate water intrusion into the lower level caused by operations on the first-floor, and to enhance the facility's structural integrity and long-term durability.
end
body
Recommended Action
Adopt the Resolution
Prior Board Action
The Village Board approved funding for the program as part of the Fiscal Year 2025 Capital Improvement Budget on November 11, 2024 (MOT 24-264).
Background
This project constitutes the third phase of traffic coating enhancements at the Public Works Center (PWC), following the initial phases completed in 2014 and 2015. The 2025 work will address the remaining first-floor areas not included in previous efforts, along with repairs to segments of the existing membrane that are exhibiting signs of deterioration.
In coordination with this effort, a structural assessment of the facility is currently underway. Any recommended repairs resulting from that evaluation will inform the scope of work planned for implementation in 2026.
Pricing for this phase was obtained through Garland/DBS, Inc., leveraging the Omnia Partners cooperative purchasing program under Contract No. PW1925, which is included in the supporting documentation.
Staff recommends approval of the full proposed project cost of $126,192.00
Timing Considerations
Adoption at this time will allow for the project to advance on a suitable timeline in order to complete the work in 2025, prior to the commencement of s...