Skip to main content
logo

Regular Village Board meetings are typically held at 7:00 p.m., the first three Tuesdays of each month in Council Chambers of Village Hall (room 201), 123 Madison St. When a Regular Meeting falls on a holiday, the meeting typically is held the following night. The Village Board also meets in special sessions from time to time. However, dates and times of Special Meetings can vary and may change.

File #: RES 23-307    Name:
Type: Resolution Status: Passed
In control: President and Board of Trustees
On agenda: 11/20/2023 Final action: 11/20/2023
Title: A Resolution Approving a Fourth Amendment to the Professional Services Agreement Between the Village of Oak Park and Christopher B. Burke Engineering, Ltd. for Design Engineering Services for the Madison Street Streetscape Project to Change the Not to Exceed Amount from $966,444 to $992,575 and Authorizing its Execution
Attachments: 1. Resolution Amendment MadisonDesign -Burke.pdf, 2. Amendment 4 MadisonDesign Burke.pdf, 3. Sup4_MadisonSt.pdf, 4. Agreement and Amendments MadisonDesign - Burke.pdf
Submitted By
Bill McKenna, Village Engineer

Reviewed By
Ahmad M. Zayyad, Deputy Village Manager / Interim Director of Development Customer Services

Agenda Item Title
Title
A Resolution Approving a Fourth Amendment to the Professional Services Agreement Between the Village of Oak Park and Christopher B. Burke Engineering, Ltd. for Design Engineering Services for the Madison Street Streetscape Project to Change the Not to Exceed Amount from $966,444 to $992,575 and Authorizing its Execution

End
Overview
Overview
Christopher B. Burke Engineering (CBBEL) designed the Madison Street resurfacing project which was completed in 2019 and completed the design of the proposed streetscape and utility project on Madison from Oak Park Avenue to East Avenue. The proposed amendment is needed to pay for additional work required for utilizing Rebuild Illinois Funds and due to delays in the bidding due to staffing and development coordination. The amendment adjusts the existing not to exceed contract amount from $966,444 to $992,575.
End

Recommendation
Recommendation
Adopt the Resolution.

Background
Village staff has been working with Christopher Burke Engineering (CBBEL) since 2015 on the design of the Madison Street road diet and resurfacing project and the proposed streetscape and utility project from Oak Park Avenue to East Avenue. The road diet and resurfacing project was completed in 2019. The design of the streetscape and utility improvement project was completed this fall and the construction project was awarded at the October 30, 2023 Village Board meeting. There were additional costs for the design associated primarily with adding REBUILD Illinois funds to the project and some work associated with additional permitting requirements. The Village had REBUILD funds leftover from the Division Street project and the Madison Street project was a good fit for these funds but required some additional design hours to revise plans and specifications to match these...