Regular Village Board meetings are typically held at 7:00 p.m., the first three Tuesdays of each month in Council Chambers of Village Hall (room 201), 123 Madison St. When a Regular Meeting falls on a holiday, the meeting typically is held the following night. The Village Board also meets in special sessions from time to time. However, dates and times of Special Meetings can vary and may change.

File #: RES 24-110    Name:
Type: Resolution Status: Passed
In control: President and Board of Trustees
On agenda: 1/30/2024 Final action: 1/30/2024
Title: A Resolution Approving an Amendment to the Independent Contractor with J.L. Adler Roofing & Sheet Metal, Inc. for the South Fire Station Roof Replacement Project to Change the Project Completion Date and Increase the Not to Exceed Amount from $185,720.00 to $226,920.00, Authorizing its Execution and Directing Staff to Prepare the Necessary Budget Amendment for the Project
Attachments: 1. Resolution - South Station Roof Amendment - JL Adler, 2. Amendment - South Station Roof Amendment - JL Adler, 3. Attachments - South Station Roof Amendment - Contract Documents - JL Adler
Submitted By
Rob Sproule, Public Works Director

Reviewed By
Ahmad M. Zayyad, Deputy Village Manager / Interim Director of Development Customer Services

Agenda Item Title
Title
A Resolution Approving an Amendment to the Independent Contractor with J.L. Adler Roofing & Sheet Metal, Inc. for the South Fire Station Roof Replacement Project to Change the Project Completion Date and Increase the Not to Exceed Amount from $185,720.00 to $226,920.00, Authorizing its Execution and Directing Staff to Prepare the Necessary Budget Amendment for the Project

End
Overview
Overview
At the October 16, 2023 Village Board meeting, the Board approved an Independent Contractor Agreement with J.L. Adler Roofing & Sheet Metal, Inc. to replace the roof at the South Fire Station. Unexpected conditions were discovered during the demolition process that require an Amendment to the Agreement to increase to not to exceed amount of the agreement and change the project completion date...End

Recommendation
Recommendation
Adopt the Resolution.

Background
The Village Board approved an Independent Contractor Agreement with J.L. Adler Roofing & Sheet Metal, Inc. on October 16, 2023 to replace the roof at the south fire station for a total cost not to exceed $185.720.00. Work began in mid-November and during removal of the existing roof, deteriorated rotten wood was discovered along the north east section of the lower roof. The initial project completion date was December 31, 2023, however, the unexpected conditions discovered caused a delay in completing the finishing details along the perimeter of that section. Staff directed the contractor to provide a proposal cost to replace the deteriorated wood. The architect performing the construction administration on the project (Kluber, Inc.) has submitted a Construction Change Directive (CCD) describing the additional scope of work and outlining the proposed added cost. The total proposal cost to replace the deteriorated wood is a not to...