Regular Village Board meetings are typically held at 7:00 p.m., the first three Tuesdays of each month in Council Chambers of Village Hall (room 201), 123 Madison St. When a Regular Meeting falls on a holiday, the meeting typically is held the following night. The Village Board also meets in special sessions from time to time. However, dates and times of Special Meetings can vary and may change.

File #: ORD 24-102    Name:
Type: Ordinance Status: Passed
In control: President and Board of Trustees
On agenda: 2/6/2024 Final action: 2/6/2024
Title: An Ordinance Granting an Extension of Time to Complete Construction of the Planned Development at 261 Washington Boulevard to August 1, 2024
Attachments: 1. Ordinance, 2. Extension Request Letter, 3. Ordinance 21-3
Submitted By
Ahmad Zayyad, Deputy Village Manager, Acting Development Customer Services Director

Reviewed By
LKS

Agenda Item Title
Title
An Ordinance Granting an Extension of Time to Complete Construction of the Planned Development at 261 Washington Boulevard to August 1, 2024

End
Overview
Overview
Ambrosia Homes, Inc., via Tim Pomaville, is requesting approval of an extension of its planned development Ordinance deadline to allow additional time to finish construction of the multi-unit residential apartment building constructed at 261 Washington Boulevard. This is the first request to extend the development's completion date.

End
Recommendation
Recommendation
Adopt the Ordinance to allow an extension of time for the completion of construction. The applicant is requesting an additional six (6) months (from February 1, 2024, to August 1, 2024), as stated in the attached request letter. Staff supports the extension request.

Fiscal Impact
N/A

Background
The Zoning Ordinance, at the time of Planned Development approval, stated in Article 14; Section 14.5(G)2&3 that an approval of a planned development permit by the Board of Trustees shall be null and void if the recipient does not file an application for a building permit for the proposed development within twelve (12) months after Ordinance adoption, and complete the project within thirty-six (36) months. Article 14 of the Zoning Ordinance allows the Village Board to grant an extension of time, provided the applicant shows good cause in writing.

The Applicant has indicated that additional time is necessary, as stated in the attached letter dated January 11, 2024, attached hereto. Ordinance Number 21-3, approved by the Village Board on February 1, 2021, authorized the construction of a multiple-unit residential development with private parking. As of this writing, the development of the site is considerably underway. A building permit application was submitted, per the required deadline. The dev...