Regular Village Board meetings are typically held at 7:00 p.m., the first three Tuesdays of each month in Council Chambers of Village Hall (room 201), 123 Madison St. When a Regular Meeting falls on a holiday, the meeting typically is held the following night. The Village Board also meets in special sessions from time to time. However, dates and times of Special Meetings can vary and may change.

File #: RES 24-332    Name:
Type: Resolution Status: Consent Agenda
In control: President and Board of Trustees
On agenda: 11/12/2024 Final action:
Title: A Resolution Approving an Independent Contractor Agreement with National Power Rodding Corporation for the 2024 Ridgeland Ave Sewer Siphon Cleaning & Inspection Project, in an Amount not to Exceed $252,610 and Authorizing its Execution
Attachments: 1. Resolution - 2024 Siphon Cleaning.pdf, 2. Agreement - 2024 Siphon Cleaning - NPR.pdf, 3. Proposal RidgelandSewerSiphon-NPR.pdf, 4. RFP_2024 Siphon cleaning_9.27.24.pdf, 5. Siphon Drawing.pdf, 6. Siphon_Bid Summary.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Submitted By
Bill McKenna, Village Engineer/Assistant Public Works Director

Reviewed By
A.M. Zayyad, Deputy Village Manager

Agenda Item Title
Title
A Resolution Approving an Independent Contractor Agreement with National Power Rodding Corporation for the 2024 Ridgeland Ave Sewer Siphon Cleaning & Inspection Project, in an Amount not to Exceed $252,610 and Authorizing its Execution

End
Overview
Overview
Proposals were received on October 24th for the 2024 Ridgeland Ave Sewer Siphon Cleaning & Inspection Project. The only proposal was from National Power Rodding Corporation in the amount of $439,455 which is over the budgeted amount. National Power Rodding submitted an alternate proposal which included the same scope of work in an amount of $252,610. Staff recommends awarding a contract based on the alternate proposal amount of $252,610. The project consists of cleaning and inspecting the sewer siphon east of Ridgeland Ave under I-290 and providing reports of CCTV and chamber inspections.
End

Recommendation
Recommendation
Adopt the Resolution.

Background
The project consists of cleaning and television inspection of the Ridgeland Avenue sewer siphon which runs under the I-290 Expressway. The siphon and junction chambers were installed as part of the original I-290 Expressway construction and were last cleaned and inspected in 2013.

The sewer siphon is an inverted sewer siphon which drops the 7-feet diameter sewer on Ridgeland under I-290 and then has it flow back uphill to continue flowing by gravity south of I-290. This is done by changing the pipe diameter to multiple smaller pipes and changing the sewage flow from a gravity flow to a pressurized flow. An illustration showing the sewer siphon is attached for reference. Sewer siphons are a higher maintenance item as the chambers and pipes can accumulate debris and must be cleaned on a periodic basis to ensure they still function. The Sewer Siphon consists of two large junction chambers a...