Regular Village Board meetings are typically held at 7:00 p.m., the first three Tuesdays of each month in Council Chambers of Village Hall (room 201), 123 Madison St. When a Regular Meeting falls on a holiday, the meeting typically is held the following night. The Village Board also meets in special sessions from time to time. However, dates and times of Special Meetings can vary and may change.

File #: RES 23-219    Name:
Type: Resolution Status: Passed
In control: President and Board of Trustees
On agenda: 7/5/2023 Final action: 7/5/2023
Title: A Resolution Approving an Agreement with the State of Illinois for the North Avenue (IL 64) Intelligent Transportation System Project, Contract No. 62N40, in an Amount Not to Exceed $40,072, Authorizing its Execution and Approving a Funding Resolution for Said Agreement
Attachments: 1. Resolution - Agreement IDOT NorthAve ITS Project.pdf, 2. IGA IDOT North Ave 62N40.pdf, 3. Exhibit A - Cost Est.pdf, 4. Executed LOI Oak Park Phase I Rt 64 Smart Corridor 6-16-20.pdf
Submitted By
Bill McKenna, Village Engineer

Reviewed By
A.M. Zayyad, Deputy Village Manager / Interim Director of Development Customer Services

Agenda Item Title
Title
A Resolution Approving an Agreement with the State of Illinois for the North Avenue (IL 64) Intelligent Transportation System Project, Contract No. 62N40, in an Amount Not to Exceed $40,072, Authorizing its Execution and Approving a Funding Resolution for Said Agreement

End
Overview
Overview
The Illinois Department of Transportation (IDOT) has completed their design for an Intelligent Transportation System (ITS) project on North Avenue from York Road to Cicero Avenue to improve traffic flow. The project includes traffic signal improvements including fiber optic interconnections and emergency signal preemption equipment, changeable message signage, traffic surveillance equipment, and corner sidewalk ramp improvements at some locations. The Village previously approved a Letter of Intent which defined the Village's cost sharing responsibilities for the emergency traffic signal preemption equipment. This Agreement obligates the Village to pay these costs and defines maintenance responsibilities for various elements along North Avenue. IDOT anticipates bidding the project this September.

End
Recommendation
Recommendation
Adopt the Resolution.

Background
IDOT has been working on the study and design of a Smart Corridor along North Avenue for a number of years. The Smart Corridor concept uses Intelligent Transportation System (ITS) to improve travel for all modes of transportation. ITS relies heavily on technology to improve the traffic flow typically with signal upgrades and coordination.

Constructing a Smart Corridor was a recommendation of the Cook-DuPage Corridor Study and subsequent Cook-DuPage Smart Corridor Study. The Smart Corridor Study recommended a pilot project on North Avenue and on 22nd Street/Cermak since these would complement the future I-290 reconstruction pro...

Click here for full text