Legislation Details

File #: RES 26-331    Name:
Type: Resolution Status: Consent Agenda
In control: President and Board of Trustees
On agenda: 11/17/2026 Final action:
Title: A Resolution Authorizing Local Funding in an Amount not to Exceed $1,502,808 for the Federally Funded Construction and Construction Engineering of the Ridgeland Avenue Resurfacing Project, Section Number 24-00268-00-RS
Attachments: 1. 1 - Resolution.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title
title
A Resolution Authorizing Local Funding in an Amount not to Exceed $1,502,808 for the Federally Funded Construction and Construction Engineering of the Ridgeland Avenue Resurfacing Project, Section Number 24-00268-00-RS
end

Introduction
overview
The Village received $1,084,000 in federal funding for the Ridgeland Avenue resurfacing project from Augusta Street to North Avenue. The Village is required to adopt a funding Resolution committing the Village to pay the local match for the federally funded construction and construction engineering for the Ridgeland Avenue Resurfacing Project. The Village’s local share is currently estimated at $1,502,808 for construction and construction engineering using local Capital Improvement Funds and local Motor Fuel Tax funds.
end
body
Recommended Action
Adopt the Resolution.
Prior Board Action
The Board has taken the following prior actions:
The Village Board approved a Task Order with TranSystems Corporation d/b/a GFT Infrastructure, Inc. for the Phase Two Design of the Ridgeland Avenue Resurfacing Project, in an amount not to exceed $307,369 on November 11, 2025 (RES 25-272).
The Village Board approved a Task Order for Professional Engineering Services with TranSystems Corporation for the Phase One Design of the Ridgeland Avenue Resurfacing Project, in an Amount Not to Exceed $112,770 on March 5, 2024 (RES 24-145).
The Village Board approved the submission of a Federal Surface Transportation Program (STP) Grant Application for the Ridgeland Avenue Resurfacing Project on February 22, 2022 (RES 22-48).
Background
The Village received $1,084,000 in Federal Surface Transportation Program (STP) funds for resurfacing of Ridgeland Avenue from Augusta Street to North Avenue. Design of the project is complete and it is scheduled for a March 2027 bidding by IDOT for construction generally from May to October of 2027.
The project includes resurfacing of the roadway; corner sidewalk ramp improvem...

Click here for full text