Regular Village Board meetings are typically held at 7:00 p.m., the first three Tuesdays of each month in Council Chambers of Village Hall (room 201), 123 Madison St. When a Regular Meeting falls on a holiday, the meeting typically is held the following night. The Village Board also meets in special sessions from time to time. However, dates and times of Special Meetings can vary and may change.

File #: RES 24-221    Name:
Type: Resolution Status: Passed
In control: President and Board of Trustees
On agenda: 7/30/2024 Final action: 7/30/2024
Title: A Resolution Approving a Contract with William T. Connelly, Inc., d/b/a Connelly Electric Co. for Project 24-12, North Pumping Station Generator Addition, in an Amount Not to Exceed $420,000 and Authorizing its Execution
Attachments: 1. Resolution - 24-12 North Pump Station Generator - ConnellyElectric.pdf, 2. Contract & Bond_24-12 NorthPumpStation Generator ConnellyElectric.pdf, 3. Proposal 24-12 North Pump Station Generator - Connelly Electric.pdf, 4. 24-12 Bid Summary.pdf
Submitted By
Bill McKenna, Village Engineer/Assistant Public Works Director

Reviewed By
Erin E. Baynes, Assistant to the Village Manager

Agenda Item Title
Title
A Resolution Approving a Contract with William T. Connelly, Inc., d/b/a Connelly Electric Co. for Project 24-12, North Pumping Station Generator Addition, in an Amount Not to Exceed $420,000 and Authorizing its Execution

End
Overview
Overview
Competitive bids were opened on May 23, 2024 for the North Pumping Station Generator Addition Project. Five contractors picked up proposal documents and three bids were received. The low responsible bid was submitted by Connelly Electric Co. in an amount of $420,000. The project involves the installation of an emergency generator at the North Pump Station, including the concrete pad, its associated infrastructure, and electrical modifications to the building. Work is planned for completion in 2025 due to long lead times for the generator.
End

Recommendation
Recommendation
Adopt the Resolution.

Background
The North and South Pump Stations do not have permanent standby generators to supply power in the case of power failure. In the case of power loss, the Village uses a portable generator to supply power to up to one pump station. Mobilizing this portable generator creates a significant amount of down time for the affected pumping station. A permanent standby generator will help ensure timely delivery of potable drinking water. The North Pump Station is prioritized for the first generator as the South Pump Station has two independent power supplies from ComEd that create a level of redundancy. Having backup power for drinking water pumping stations is an Illinois EPA requirement.

This project involves installing a new fenced-off area at the North Pump Station which will have a concrete pad and retaining wall for the generator. It also includes the associated electrical work and new gas service for the generator. The North Pump Station is lo...