Title:
title
A Presentation on the Outcomes of the Design Charrette Process for Schematic Design of the Oak Park Municipal Campus Project.
end
Introduction
overview
As part of the Oak Park Municipal Campus schematic design process, the design team worked with Village staff to solicit feedback from community members and Village Hall users to inform Open House (1/22/2025) and Charrette Day (1/31/2025) activities. The schematic design team will summarize the feedback received, the outcomes of the Open House and Charrette Day activities, and solicit additional feedback from the Village Board based on the information presented.
end
body
Recommended Action
Village staff are not seeking Village Board action as part of this presentation.
Prior Board Action
* On December 3, 2024, the Village Board approved a resolution for a Professional Services Agreement with Johnson Lasky Kindelin Architects, Inc. for Schematic Design Architectural Services for the Oak Park Municipal Campus (RES 24-358).
* On November 21, 2024, the Village Board approved the Motion to direct staff to negotiate a professional services agreement with Johnson Lasky Kindelin Architects, Inc. for schematic design architectural services for the Oak Park Municipal Campus (MOT 24-269).
* On July 30, 2024, Village staff brought forth a resolution for an amendment to the professional services agreement with Johnson Lasky Kindelin Architects, Inc. for additional conceptual solutions for village facilities. The Village Board denied this resolution and instead came to a consensus to move forward with the original Option 3, to build a new police station on the existing site and make renovations to the existing Village Hall. The Village Board directed staff to work through the process of choosing an architect to set the project's budget and prioritize the Village's needs (RES 24-261).
* On May 28, 2024, Ludwig Speaks facilitated a discussion with the Village Board to affirm their prio...
Click here for full text