Skip to main content
logo

Regular Village Board meetings are typically held at 7:00 p.m., the first three Tuesdays of each month in Council Chambers of Village Hall (room 201), 123 Madison St. When a Regular Meeting falls on a holiday, the meeting typically is held the following night. The Village Board also meets in special sessions from time to time. However, dates and times of Special Meetings can vary and may change.

File #: RES 23-138    Name:
Type: Resolution Status: Passed
In control: President and Board of Trustees
On agenda: 4/24/2023 Final action: 4/24/2023
Title: A Resolution Approving an Amendment to the Professional Services Agreement with FGM Architects Inc. for Professional Architectural Services for Additional Conceptual Solutions for Village Facilities to Change the Not to Exceed Amount from $25,000 to $36,000 and Authorizing its Execution
Attachments: 1. Resolution - Amendment to Architectural Services Agreement - FGM, 2. Amendment - Architectural Services Agreement - FGM, 3. Attachment - Oak Park PD Additional Options Proposal 2023.03.22, 4. Attachments - Contract Documents - Architectural Services Agreement - FGM
Submitted By
Rob Sproule, Public Works Director

Reviewed By
A.M. Zayyad, Deputy Village Manager

Agenda Item Title
Title
A Resolution Approving an Amendment to the Professional Services Agreement with FGM Architects Inc. for Professional Architectural Services for Additional Conceptual Solutions for Village Facilities to Change the Not to Exceed Amount from $25,000 to $36,000 and Authorizing its Execution

End
Overview
Overview
FGM Architects, Inc. is currently under contract to provide professional architectural services connected with Village facilities. Staff are requesting to amend the agreement with FGM Architects, Inc. to increase the not to exceed amount by $11,000.00 to evaluate an additional design option prior to evaluation by the Village Board.

End
Recommendation
Recommendation
Adopt the Resolution.

Background
In June of 2022, Staff provided the Village Manager and Village Board an update on the current state of the proposed Village facilities. Part of the update provided an overview of the Space Needs Assessment completed by FGM Architects in 2019.

Following those conversations with the Village Board, Staff was directed to reengage FGM Architects to evaluate additional possible conceptual options and update the costs for the existing option, as the original numbers were generated in late 2019.

After reviewing the information and updated costs provided by FGM during this latest update, it was determined an additional option should be evaluated before a decision is made on the preferred option for schematic design.

Staff are requesting to amend the existing professional services agreement by $11,000.00 for a total not to exceed amount of $36,000.00 for further evaluation of an additional design option prior to presenting to the board in late June or early July for a determination on the proposed option to advance to schematic design.

Fiscal Impact
There are sufficient unencumbered funds in the Building Improvement Fund Acco...

Click here for full text