Regular Village Board meetings are typically held at 7:00 p.m., the first three Tuesdays of each month in Council Chambers of Village Hall (room 201), 123 Madison St. When a Regular Meeting falls on a holiday, the meeting typically is held the following night. The Village Board also meets in special sessions from time to time. However, dates and times of Special Meetings can vary and may change.

File #: RES 23-206    Name:
Type: Resolution Status: Passed
In control: President and Board of Trustees
On agenda: 6/20/2023 Final action: 6/20/2023
Title: A Resolution Approving a Contract with Morrison Construction Company, Inc. for Project 23-12, North and South Pumping Station Upgrades, in an Amount Not to Exceed $396,500 and Authorizing its Execution
Attachments: 1. Resolution - 23-12 NorthSouthStation Rehab.pdf, 2. Contract and Bond 23-12 North-South Pump Station Morrison.pdf, 3. Proposal 23-12 NorthSouthPumpStation - Morrison.pdf, 4. 23-12 Bid Summary.pdf
Submitted By
Bill McKenna, Village Engineer

Reviewed By
A.M. Zayyad, Deputy Village Manager

Agenda Item Title
Title
A Resolution Approving a Contract with Morrison Construction Company, Inc. for Project 23-12, North and South Pumping Station Upgrades, in an Amount Not to Exceed $396,500 and Authorizing its Execution

End
Overview
Overview
The Engineering Division opened bids for Project 23-12, North and South Pumping Station Upgrades. The project includes rebuilding four existing older pumps at the north and south pumping stations and replacing worn-out check valves, couplings, and flow switches at these stations in order to improve pumping efficiencies and ensure reliability. Five contractors picked up bid documents and three bids were received. The lowest responsible bid was submitted by Morrison Constriction Company in an amount of $396,500, which is over the budgeted amount for this project. There are available funds from deferred projects to cover the additional costs. Construction work is planned to start this fall following the completion of work in the central pump station and last until 2024 due to long lead times on materials.

End
Recommendation
Recommendation
Adopt the Resolution.

Background
The Engineering Division opened bids for Project 23-12 on June 1st. The low bid was submitted by Morrison Constriction Company, Inc. in an amount of $396,500. This amount is under the engineer's estimate of $415,000 for the project and reflects a competitive bid for the work. However, the low bid is over the budgeted amount for this project. The 2023 Budget for the project did not include work for replacing three defective check valves, isolation couplings, switches, and replacing a section of piping. These items were identified for replacement based on their condition and impacts on efficiencies when a detailed examination of the pump station systems was performed during the scoping for the design of the project in the fall of 2...