A Resolution Approving a Task Order for Professional Engineering Services with Baxter & Woodman, Inc. for Design Engineering Services for the 24-1 Water and Sewer Improvement Project in an Amount Not to Exceed $107,900 and Authorizing its Execution
End
Overview
Overview
The Engineering Division of the Public Works Department requested a proposal from Baxter & Woodman to provide design engineering for the 24-1 Water and Sewer Improvement Project. Baxter & Woodman has previously designed similar projects and has substantially completed design for one of the project's locations, which was originally planned for 2023 construction but was deferred to 2024. The project includes water and sewer replacement and street reconstruction on South Boulevard from Home Avenue to Kenilworth Avenue; sewer replacement and street reconstruction on Linden Avenue from Augusta Street to Thomas Street; and sewer lining on Woodbine Avenue from Division Street to Greenfield Street and on Ontario Street from East Avenue to Scoville Avenue.
End
Recommendation
Recommendation
Adopt the Resolution.
Background
The Engineering Division of the Public Works Department requested a proposal from Baxter & Woodman to provide design engineering services for the proposed 2024 Water and Sewer Improvement project 24-1. The project includes sewer and water main replacement and roadway reconstruction at one location; sewer main and roadway reconstruction at one location; and sewer rehabilitation using a trenchless lining method at two locations.
The planned work on Linden Avenue from Augusta Street to Thomas Street includes sewer main replacement due to deteriorated conditions identified during sewer televising inspection and roadway reconstruction.
The planned work on Woodbine Avenue from Division Street to Gree...