Skip to main content
logo

Regular Village Board meetings are typically held at 7:00 p.m., the first three Tuesdays of each month in Council Chambers of Village Hall (room 201), 123 Madison St. When a Regular Meeting falls on a holiday, the meeting typically is held the following night. The Village Board also meets in special sessions from time to time. However, dates and times of Special Meetings can vary and may change.

File #: RES 24-005    Name:
Type: Resolution Status: Passed
In control: President and Board of Trustees
On agenda: 1/23/2024 Final action: 1/23/2024
Title: A Resolution Approving an Independent Contractor Agreement with Omni Pump Repairs, Inc. to Replace the Domestic Water Booster Pump System at the Public Works Center in an Amount Not to Exceed $57,723.75 and Authorizing its Execution
Attachments: 1. Resolution - PWC Booster Pump Replacement- Omni Pump Repairs, Inc., 2. Omni Pump ICA, 3. Attachments - PWC Booster Pump Replacement - Omni Pump Repairs, Inc.
Submitted By
Rob Sproule, Public Works Director

Reviewed By
A.M. Zayyad, Deputy Village Manager

Agenda Item Title
Title
A Resolution Approving an Independent Contractor Agreement with Omni Pump Repairs, Inc. to Replace the Domestic Water Booster Pump System at the Public Works Center in an Amount Not to Exceed $57,723.75 and Authorizing its Execution

End
Overview
Overview
The water booster pump system at the Public Works Center is original to the building circa 2007. The system contains two pump drives, one of which has failed and it is recommended that both pumps be replaced. End

Recommendation
Recommendation
Adopt the Resolution.

Background
The domestic water booster pump system at the Public Works Center (PWC) is original to the building circa 2007. The booster system ensures that adequate and consistent water pressure is delivered throughout the entire building. The system contains two pump drives, one of which failed towards the end of 2022. The failed pump drive cannot be repaired and needs to be replaced. The other pump is still functioning but has reached the end of its useful service life. With only one working pump, the current water pressure is below average, and if the remaining pump fails, the building water pressure could fall substantially. The Property Condition Assessment (PCA) of the PWC completed in 2023 identified the system as being due for replacement.

Staff issued a Request for Proposals (RFP) on November 15, 2023. The RFP was posted on the Village web page and in the Wednesday Journal. Three companies attended the pre-bid meeting on November 27, 2023. Proposals were due on Wednesday, November 29, 2023, and a total of two proposals were received. Omni Pump Repairs, Inc. submitted the most favorable proposal and staff recommends the Village approve an agreement with Omni Pump Repairs.

Fiscal Impact
The Fiscal Year 2024 CIP Building Improvement Fund includes a total of $2,832,885.00 in account # 3012-43790-101-540673. $...

Click here for full text