Title
title
A Resolution Approving a Task Order with TranSystems Corporation d/b/a GFT Infrastructure, Inc. for the Phase Two Design of the Ridgeland Avenue Resurfacing Project, in an Amount not to Exceed $307,369 and Authorizing its Execution
end
Introduction
overview
The Engineering Division requested a proposal from TranSystems Corporation to do the Phase Two (final) design for the 2027 Ridgeland Avenue Resurfacing Project. The future resurfacing project includes street resurfacing on Ridgeland from Augusta to North Avenue, traffic signal replacement at the Division intersection, and safety improvements at multiple intersections. The future construction project is using federal funds and therefore the design must go through the formal phase one and two design process and IDOT approval.
end
body
Recommended Action
Adopt the Resolution.
Prior Board Action
The Board has taken the following prior actions:
* The Village Board approved a Task Order for Professional Engineering Services with TranSystems Corporation for the Phase One Design of the Ridgeland Avenue Resurfacing Project, in an Amount Not to Exceed $112,770 on March 5, 2024 (RES 24-145)
* The Village Board approved a Renewal of the Master Agreement with TranSystems Corporation for Professional Engineering Services in 2025 on December 3, 2024 (RES 24-386)
* The Village Board approved a Master Agreement for Professional Engineering Services with TranSystems Corporation on September 21, 2021. (RES 21-221)
* The Village Board approved the submission of a Federal Surface Transportation Program (STP) Grant Application for the Ridgeland Avenue Resurfacing Project on February 22, 2022 (RES 22-48)
Background
The Engineering Division requested a proposal from TranSystems Corporation (now doing business as GFT Infrastructure, Inc.) to perform the Phase II design of a resurfacing project on Ridgeland Avenue from Augusta to North Avenue. TranSystems has completed the preliminary (Phase I) ...
Click here for full text