Regular Village Board meetings are typically held at 7:00 p.m., the first three Tuesdays of each month in Council Chambers of Village Hall (room 201), 123 Madison St. When a Regular Meeting falls on a holiday, the meeting typically is held the following night. The Village Board also meets in special sessions from time to time. However, dates and times of Special Meetings can vary and may change.

File #: RES 21-137    Name:
Type: Resolution Status: Passed
In control: President and Board of Trustees
On agenda: 6/24/2021 Final action: 6/24/2021
Title: A Resolution Approving an Independent Contractor Agreement with MYS, Incorporated for Chicago Avenue Brick Crosswalk Repairs in an Amount Not to Exceed $60,000.00 and Authorizing its Execution
Attachments: 1. Resolution MYS Agreement, 2. Agreement-Chicago Ave. Crosswalk Repairs, 3. Attachment-Bid Summary- Chicago Ave. Croswalk Repairs, 4. Attachment-MYS Bid, 5. Attachment_Certificate of Good Standing-MYS, Inc., 6. Attachment-FY21-25 Adopted CIP, 7. Attachment-RFB.Chicago Ave. Crosswalk Project #21-128, 8. Attachment-Addendum Chicago Ave. Crosswalk Repairs
Submitted By
John P. Wielebnicki, Public Works Director

Reviewed By
AMZ

Agenda Item Title
Title
A Resolution Approving an Independent Contractor Agreement with MYS, Incorporated for Chicago Avenue Brick Crosswalk Repairs in an Amount Not to Exceed $60,000.00 and Authorizing its Execution

End
Overview
Overview
The Public Works Department is responsible for the repair and maintenance of all Village streets and sidewalks. The brick paver crosswalks located at the intersections of Chicago/Harvey and Chicago/Humphrey are in need of replacement. MYS, Incorporated is the lowest responsible bidder for this work.

End
Recommendation
Recommendation
Approve the Resolution.

Fiscal Impact
In the Fiscal Year 2021 Capital Improvement Fund, there is $60,000.00 for maintenance and repair of brick streets and alleys in account no., 3095-43780-101-570951.

The lowest responsible bid was submitted by MYS, Incorporated for $56,997.00. It is requested to authorize the entire budget amount of $60,000.00 in the event additional work is found to be required when work starts.

Background
The Village is responsible for maintaining the brick paver crosswalks along Chicago Ave. The brick paver crosswalks at the Chicago/Harvey and Chicago/Humphrey intersections require replacement. The brick crosswalks were originally installed in 2006 as part of the Chicago Ave. Streetscape project. This project was included in the 2021 Capital Improvement Fund. The project sheet is included for reference.

Competitive bids were opened on May 25, 2021, in response to a call for bids for the Chicago Avenue Crosswalks Rehab Project which was sent out on May 5, 2021. The call for bids was posted in the Wednesday Journal and on the Village website. Four contractors were contacted directly. Two bids were received.

MYS, Incorporated, has done this and other types of work for the Village in the past. They have provided responsive and quality work.

Alternatives
The Village Board could dela...