Title
title
A Resolution Approving a Contract with Strada Construction Company for project 26-3, Sidewalk Improvements, in an amount Not to Exceed $435,109 and Authorizing its Execution
end
Introduction
overview
Competitive bids were opened on May 14, 2026 for Project 26-3, Sidewalk Improvements. Five contractors downloaded the bid documents, and two bids were received. The low responsible bid was submitted by Strada Construction Company in an amount of $235,242.00. The low bid is under the budgeted amount, and staff recommends awarding the contract at the available budget amount of $435,109 in order to utilize CDBG Funds that must be expended and replace needed sidewalks. The work includes sidewalk replacement predominantly along north-south streets in the southeast part of the Village.
end
body
Recommended Action
Adopt the Resolution.
Prior Board Action
There is no prior Board action associated with this item.
Background
This project includes the replacement of approximately 18,500 square feet of sidewalks (about 750 sidewalk squares), as well as additional quantities for curbs, driveway apron replacement, and other items associated with this concrete work. Sidewalk replacement will take place at numerous locations throughout the Village, but is predominantly for sidewalk replacements along the north-south streets in the southeast portion of the Village this year. A map showing general locations for sidewalk replacement is attached. Construction is scheduled to be completed by October 31, 2026.
Sidewalk locations have been prioritized based on a sidewalk survey conducted by the Engineering Division staff. Staff surveys approximately one-sixth of the Village each year, with work focused on north-south streets in the northwest portion of the Village this year. Sidewalks that have elevation differences of 1/2" or more between adjacent slabs are scheduled for replacement in order to remove barriers for persons with disabilities or the e...