Regular Village Board meetings are typically held at 7:00 p.m., the first three Tuesdays of each month in Council Chambers of Village Hall (room 201), 123 Madison St. When a Regular Meeting falls on a holiday, the meeting typically is held the following night. The Village Board also meets in special sessions from time to time. However, dates and times of Special Meetings can vary and may change.

File #: RES 24-338    Name:
Type: Resolution Status: Consent Agenda
In control: President and Board of Trustees
On agenda: 11/19/2024 Final action:
Title: A Resolution Approving an Amendment to the Task Order for Professional Engineering Services with V3 Companies, Ltd. for Construction Engineering Services for the 24-7 Austin Boulevard Sewer Improvements Project to Change the not to Exceed Amount from $76,493 to $95,493 and Authorizing its Execution
Attachments: 1. Resolution - AmendmentAustinSewerCE - V3.pdf, 2. Amendment TaskOrder AustinSewer Engineering - V3.pdf, 3. Attachment B - RequestAmendment.pdf, 4. TaskOrder Austin Sewer Eng - V3.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Submitted By
Bill McKenna, Assistant Public Works Director/Village Engineer

Reviewed By
A.M. Zayyad, Deputy Village Manager

Agenda Item Title
Title
A Resolution Approving an Amendment to the Task Order for Professional Engineering Services with V3 Companies, Ltd. for Construction Engineering Services for the 24-7 Austin Boulevard Sewer Improvements Project to Change the not to Exceed Amount from $76,493 to $95,493 and Authorizing its Execution

End
Overview
Overview
V3 Companies has been overseeing the construction of the Austin Boulevard Sewer Improvement Project being constructed by Millennium Contracting. The construction project experienced delays primarily associated with permitting requirements from Union Pacific Railroad and by Illinois Department of Transportation which resulted in V3 having to oversee the project beyond the anticipated hours in their original Task Order and proposal.
End

Recommendation
Recommendation
Adopt the Resolution.

Background
V3 Companies has been overseeing the construction of the Austin Boulevard Sewer Improvement Project being constructed by Millennium Contracting. The construction project experienced delays primarily associated with permitting requirements from Union Pacific Railroad and by Illinois Department of Transportation (IDOT) which resulted in V3 having to oversee the project beyond the anticipated hours in their original Task Order and proposal.

The Union Pacific (UP) permitting delays were associated with UP issuing approvals for the contractor to start work for inspecting and repairing the sewer and replacing the roadway under the UP viaduct between North and South Boulevards. The IDOT permitting delays were associated with the IDOT permit for traffic control associated with the emergency water supply disconnection at the Roosevelt Road and Austin Boulevard intersection. These delays were outside of V3 or the contractor's ability to control but extended the duration of the project. Overall ...