Regular Village Board meetings are typically held at 7:00 p.m., the first three Tuesdays of each month in Council Chambers of Village Hall (room 201), 123 Madison St. When a Regular Meeting falls on a holiday, the meeting typically is held the following night. The Village Board also meets in special sessions from time to time. However, dates and times of Special Meetings can vary and may change.

File #: RES 15-228    Name:
Type: Resolution Status: Passed
In control: President and Board of Trustees
On agenda: 3/16/2015 Final action: 3/16/2015
Title: A Resolution Authorizing Execution of a Professional Services Agreement with Terra Engineering, Ltd. for Professional Engineering Services for Design and Construction Engineering of the Harrison Street Lighting Improvement Project in an amount not to exceed $91,378.23.
Attachments: 1. 03-16-15_AttachmentB_15-17HarrisonStreetLightingEngineering, 2. 03-16-15_AttachmentC_15-17HarrisonStLightingImprovementsProjectLocationMap, 3. 03-16-15_AttachmentD_TerraEngineeringProposal.pdf, 4. 03-16-15_Resolution-15-17HarrisonStreetLightingEngineering.pdf, 5. 03-16-15_AttachmentA_ProfessionalServicesAgreement_15-17.pdf
Submitted By
Bill McKenna, Village Engineer

Reviewed By
LKS

Agenda Item Title
Title
A Resolution Authorizing Execution of a Professional Services Agreement with Terra Engineering, Ltd. for Professional Engineering Services for Design and Construction Engineering of the Harrison Street Lighting Improvement Project in an amount not to exceed $91,378.23.

End
Overview
Overview
This item provides for engineering and design for a new street lighting system for the Harrison Street Arts District. Department of Public Works staff solicited proposals from engineering consultants for these professional services and Terra Engineering, Ltd. provided the most favorable proposal for this project.

Body
Staff Recommendation
Approve the Resolution.

Fiscal Impact
The monies for this Project would be funded through the FY 2015 Capital Improvement Fund, account no. 3095-43780-101-570954 which provides $1,035,000.00 for design and construction engineering.

Background
In 2007 the Village and the Harrison Arts District worked on an Urban Design Plan which included various streetscape projects. Street lighting was one of improvements outlined from the plan.

The Engineering Division opened proposals on March 5, 2015 for the design and construction engineering services for the 2015 Harrison Street Lighting Improvement Project. A total of five engineering firms received proposal documents and four proposals were received.

The proposal from Terra Engineering, Ltd. best fit the project scope at a competitive price. The scope of services covered under this agreement includes the design and construction management of the Project.

The Project involves the replacement of the street and pedestrian-level LED lighting through the Oak Park Arts District, along Harrison Street from Elmwood Avenue to Austin Boulevard. New decorative lighting on Lombard Avenue from Harrison St. to the alley south of Harrison St. and potentially a pedestrian-level li...