Regular Village Board meetings are typically held at 7:00 p.m., the first three Tuesdays of each month in Council Chambers of Village Hall (room 201), 123 Madison St. When a Regular Meeting falls on a holiday, the meeting typically is held the following night. The Village Board also meets in special sessions from time to time. However, dates and times of Special Meetings can vary and may change.

File #: RES 15-242    Name:
Type: Resolution Status: Passed
In control: President and Board of Trustees
On agenda: 3/16/2015 Final action: 3/16/2015
Title: A Resolution Authorizing the Execution of a Contract with J. Nardulli Concrete, Inc., for Project 15-4, 2015 Alley Improvements, in an amount not to exceed $1,486,455.00.
Attachments: 1. 03-16-15_Resolution-15-4AlleyImprovements.pdf, 2. 03-16-15_AttachmentA_Contract_15-4 Alley Improvements.pdf, 3. 03-16-15_AttachmentB_15-4 Bid Summary.pdf, 4. 03-16-15_AttachmentC_15-4 AlleyImprovements LocationMap.pdf, 5. 03-16-15_AttachmentD_NardulliProposal15-4.pdf
Submitted By
Bill McKenna, Village Engineer

Reviewed By
LKS

Agenda Item Title
Title
A Resolution Authorizing the Execution of a Contract with J. Nardulli Concrete, Inc., for Project 15-4, 2015 Alley Improvements, in an amount not to exceed $1,486,455.00.

End
Overview
Overview
Competitive bids were opened on March 5, 2015, for the Alley Improvements Project. Ten contractors picked up bid documents and six bids were received. The low responsible bid was submitted by J. Nardulli Concrete, Inc. in an amount of $1,486,455.00.

Body
Staff Recommendation
It is recommended that a contract be awarded to J. Nardulli Concrete, Inc. in an amount not to exceed the bid amount of $1,486,455.00.

Fiscal Impact
The costs for this project would be funded through the Capital Improvement Fund account no. 3095-43780-101-570964 which provides $2,700,000.00 for design and construction.

Background
This project includes the removal and concrete-installation of fifteen alley segments at various locations south of South Blvd. The alleys being replaced with this contract have condition score ranges in the 20's through 50's with 100 being a newly constructed alley. An attachment shows the specific work locations in this contract.

This contract is the first of two alley construction contracts being awarded in 2015. The second contract is tentatively scheduled to be brought forward for consideration at the May 18th Village Board meeting. The second contract consists of the alleys to be reconstructed in the northern portion of the Village this year.

Alternatives
The alternative to this recommendation is to not award the contract.

Previous Board Action
On November 3, 2014 the Village Board authorized a contract with Hancock Engineering to design and manage the alley improvement projects for 2015.

Citizen Advisory Commission Action
N/A.

Anticipated Future Actions/Commitments
The second alley contract is tentatively scheduled to be brough...