Regular Village Board meetings are typically held at 7:00 p.m., the first three Tuesdays of each month in Council Chambers of Village Hall (room 201), 123 Madison St. When a Regular Meeting falls on a holiday, the meeting typically is held the following night. The Village Board also meets in special sessions from time to time. However, dates and times of Special Meetings can vary and may change.

File #: ORD 15-086    Name:
Type: Ordinance Status: Passed
In control: President and Board of Trustees
On agenda: 4/20/2015 Final action: 4/20/2015
Title: Second Reading and Adoption of an Ordinance Amending Chapter 7 ("Buildings"), Article 8 ("Fees") of the Oak Park Village Code to Establish an Annual Building and Construction Permit Fees and Zoning Application Fees Ordinance Requirement.
Attachments: 1. Permit Fees Code Amendments 04-03-15
Submitted By
Tammie Grossman, Director Development Customer Services

Reviewed By
CLP

Agenda Item Title
Title
Second Reading and Adoption of an Ordinance Amending Chapter 7 ("Buildings"), Article 8 ("Fees") of the Oak Park Village Code to Establish an Annual Building and Construction Permit Fees and Zoning Application Fees Ordinance Requirement.

End
Overview
Overview
The First Reading of the Ordinance was held on March 16, 2015. The Building Construction Permit Fee and Zoning Application Fee Schedule have not been fully updated since July 2009 and a comprehensive review has been completed resulting in the recommended amendment to the Village Code to establish a new schedule that reflects the current cost of providing services. Additionally, the recommended amendment provides that on an annual basis, the fee schedule should be reviewed and adjusted to ensure that the fees charged accurately reflect any fluctuation in the cost of providing services.

Body
Staff Recommendation
Conduct second reading and adopt the Ordinance.

Fiscal Impact
The Building Construction Permit Fees and Zoning Application Fee Schedule has been revised to reflect the current cost of providing services and should, therefore, result in a revenue neutral state for the Permit Processing Division's annual budget.

Background
The First Reading of the Ordinance was held on March 16, 2015. Upon review, Public Works revised the attached fee schedule and increased some fees to cover costs. Changes requested by Public Works are related to sewer connection fees and eliminating certain water meter accessory fees. The revised Fee Schedule also clarifies plan review fees for Fire Department review of fire protection and detection systems and the plan review fees for Health Department review of food service establishment projects. The revised restoration deposit requirements eliminate deposit amounts being determined by the Director of Public Works on a case-by-case basis...

Click here for full text