Regular Village Board meetings are typically held at 7:00 p.m., the first three Tuesdays of each month in Council Chambers of Village Hall (room 201), 123 Madison St. When a Regular Meeting falls on a holiday, the meeting typically is held the following night. The Village Board also meets in special sessions from time to time. However, dates and times of Special Meetings can vary and may change.

File #: RES 17-554    Name:
Type: Resolution Status: Passed
In control: President and Board of Trustees
On agenda: 7/17/2017 Final action: 7/17/2017
Title: A Resolution Approving an Independent Contractor Agreement with Chicagoland Renovations, Inc. for the North Fire Station Bunk Room, Stairway and Bathroom Remodeling Project in an Amount Not to Exceed $86,500.00 and Authorizing its Execution
Attachments: 1. 06-05-17-Resolution-Chicagoland Renovations, 2. 06-05-17-Independent Contractor Agreement-Chicagoland Renovations, 3. 06-05-17-Attachment-Proposal Summary-North Fire Station, 4. 06-05-17-Attachment-Chicagoland Renovations RFP, 5. 06-05-17-Attachment-Chicagoland Renovations Addendum 1, 6. 06-05-17-Attachment-Chicagoland Renovations SOS
Submitted By
John P. Wielebnicki, Director of Public Works

Reviewed By
LKS

Agenda Item Title
Title
A Resolution Approving an Independent Contractor Agreement with Chicagoland Renovations, Inc. for the North Fire Station Bunk Room, Stairway and Bathroom Remodeling Project in an Amount Not to Exceed $86,500.00 and Authorizing its Execution

End
Overview
Overview
The CIP Building Improvement Fund includes a remodeling project at the north fire station that staff identified as a priority for 2017. The project involves the remodeling of the second floor bunk room, stairway to second floor and first floor bathroom and staff recommends moving forward with this project to improve the conditions at the north fire station.

Body
Staff Recommendation
Approve the Resolution.

Fiscal Impact
The FY 2017 Capital Improvement Building Improvement Fund Budget provides a total of $90,000 for the north fire station bunk room, first floor (apparatus floor) bathroom and stairway to second floor remodeling project in account no. 3012-43790-101-540673. $50,000 is budgeted for the bunk room, $10,000 is budgeted for the apparatus floor bathroom and $30,000 is budgeted for the stairway. To date, no funds have been spent for this work.

The proposed not to exceed amount of this contract would be $86,500.00 - total proposal base bid cost of $78,680.00 plus $7,820 (approx 10%) for unforeseen conditions or unanticipated changes to the scope of work.

Background
The Department of Public Works issued a Request for Proposals on March 22nd, 2017 for the north fire station bunk room, stairway and bathroom project. A pre-proposal meeting was held on March 29th. Four contractors attended the meeting. Four proposals were received. Builders Land, Inc. submitted the lowest proposal, but later retracted their proposal thereby forfeiting their bid bond. Chicagoland Renovations submitted the next lowest proposal. Chicagoland Renovations recently completed the soundproofing projec...

Click here for full text