Regular Village Board meetings are typically held at 7:00 p.m., the first three Tuesdays of each month in Council Chambers of Village Hall (room 201), 123 Madison St. When a Regular Meeting falls on a holiday, the meeting typically is held the following night. The Village Board also meets in special sessions from time to time. However, dates and times of Special Meetings can vary and may change.

File #: RES 17-590    Name:
Type: Resolution Status: Passed
In control: President and Board of Trustees
On agenda: 7/17/2017 Final action: 7/17/2017
Title: A Resolution Approving an Independent Contractor Agreement with S.E.P.S., Inc. for the Village Hall Uninterruptable Power Supply (UPS) Replacement Project in an Amount Not to Exceed $36,005.00 and Authorizing its Execution
Attachments: 1. Resolution-UPS, 2. Independent Contractor Agreement-UPS-SEPS, 3. Attachment-UPS-SEPS Bid, 4. Attachment-Bid Tab.VH UPS.5.31.17, 5. Attachment-UPS-Request for Bids, 6. Attachment-UPS-Corporation File Detail Report-6-26-17
Submitted By
John P. Wielebnicki, Director of Public Works

Reviewed By
LKS

Agenda Item Title
Title
A Resolution Approving an Independent Contractor Agreement with S.E.P.S., Inc. for the Village Hall Uninterruptable Power Supply (UPS) Replacement Project in an Amount Not to Exceed $36,005.00 and Authorizing its Execution

End
Overview
Overview
The 2017 CIP Building Improvement Fund includes the replacement of the existing UPS at Village Hall with a new UPS system. The existing UPS has reached the end of its useful service life.

Body
Staff Recommendation
Approve the Resolution.

Fiscal Impact
The FY 2017 Capital Improvement Building Improvement Fund Budget provides a total of $50,000.00 for the replacement of the Village Hall UPS system in account no. 3012-43790-101-540673. No funds have been spent to date.

The proposed not to exceed amount of this contract would be $36,005.00. This is the total proposal cost of $34,290.94 plus 5% to cover any unforeseen conditions or required changes to the scope during installation of new system. The 5% is in accordance with the purchase policy regarding change orders.

Background
The UPS system (Uninterruptable Power Supply) at Village Hall is a critical system of the Information Technology (IT) Department that provides continuous power to the Village's computer network during a power outage. The existing system has reached the end of its useful service life and is in need of replacement.

The Department of Public Works issued a Request for Proposals on May 3rd, 2017 for the replacement of the Village Hall UPS. A pre-proposal meeting was held on May 9th. Three contractors attended the meeting. Two proposals were received on May 31st, 2017. SEPS, Inc. submitted the lowest proposal and the IT Department has recommended the approval of an Independent Contractor Agreement with SEPS, Inc. for this project. The proposed agreement includes purchasing the UPS equipment, installation and a 3rd year extended war...