Regular Village Board meetings are typically held at 7:00 p.m., the first three Tuesdays of each month in Council Chambers of Village Hall (room 201), 123 Madison St. When a Regular Meeting falls on a holiday, the meeting typically is held the following night. The Village Board also meets in special sessions from time to time. However, dates and times of Special Meetings can vary and may change.

File #: RES 17-651    Name:
Type: Resolution Status: Passed
In control: President and Board of Trustees
On agenda: 10/2/2017 Final action: 10/2/2017
Title: A Resolution Approving a Contract with MYS, Incorporated, for Project 17-26, Lake Street Sidewalk Repairs, in an Amount not to Exceed $37,950 and Authorizing its Execution
Attachments: 1. 10-02-17_Resolution-17-26_LakeStSidewalk_MYS.pdf, 2. 10-02-17_AttachmentA_Contract17-26_LakeStSidewalkRepairs.pdf, 3. 10-02-17_attachmentB_17-26 _LakeStSidewalk_BidSummary.pdf, 4. 10-02-17_AttachmentC_17-26_LakeStSidewalk_MYSproposal.pdf

Submitted By                     

Bill McKenna, Village Engineer

 

Reviewed By

LKS

 

Agenda Item Title

Title

A Resolution Approving a Contract with MYS, Incorporated, for Project 17-26, Lake Street Sidewalk Repairs, in an Amount not to Exceed $37,950 and Authorizing its Execution

 

End

Overview

Overview

The Engineering Division opened bids on September 14, 2017 for the Lake Street Sidewalk Repairs project. Five contractors received proposal documents and two bids were received. The lowest responsible bid being submitted by MYS, Inc., in an amount of $37,950.

 

Body

Staff Recommendation

Approve the Resolution

 

Fiscal Impact

The FY2017 budget includes $25,000 in funds for this project in the Capital Improvement Fund, Public Works - Engineering, Streetscaping Account no. 3095-43780-101-570959 for Paver brick and tree pit/in ground planter maintenance. 

 

The bid amount of $37,960 is over the budgeted amount by $12,950.  There are available funds in the same Capital Improvement Fund, Public Works - Engineering, Streetscaping Account no. 3095-43780-101-570959 from unspent funds from savings for the Colt Site Streetscaping to fund the remaining $12,950 needed for this work.   

 

Background

The Village allocates $25,000 annually to replace damaged or missing paver bricks, repairing tree pits and improve the aesthetics in various business districts. The project this year focuses on Lake St between Harlem Ave and Forest Ave. This maintenance work will eliminate trip hazard liabilities throughout this stretch of busy streetscape while a long term plan for this area is being determined.

 

Alternatives

The alternative to this recommendation could be to delay action to gain additional information.

 

Previous Board Action

N/A.

 

Citizen Advisory Commission Action

N/A.

 

Anticipated Future Actions/Commitments

None at this time.

 

Intergovernmental Cooperation Opportunities

None at this time.

 

Performance Management (MAP) Alignment

This work is in alignment with the Governance Priority for the Department of Public Works for Infrastructure/Capital Programs.