Regular Village Board meetings are typically held at 7:00 p.m., the first three Tuesdays of each month in Council Chambers of Village Hall (room 201), 123 Madison St. When a Regular Meeting falls on a holiday, the meeting typically is held the following night. The Village Board also meets in special sessions from time to time. However, dates and times of Special Meetings can vary and may change.

File #: RES 18-845    Name:
Type: Resolution Status: Passed
In control: President and Board of Trustees
On agenda: 3/19/2018 Final action: 3/19/2018
Title: A Resolution Approving a Change Order for the Construction of the South Boulevard Streetscape Project, Section 13-00256-00-PV, in an Amount Not to Exceed $143,500
Attachments: 1. 03-19-18_Resolution_ChangeOrderSouthBlvd, 2. ChangeOrderSummarySouthBlvd, 3. LAA_13-00256_SouthBlvd_Executed
Submitted By
Bill McKenna, Village Enginer

Reviewed By
LKS

Agenda Item Title
Title
A Resolution Approving a Change Order for the Construction of the South Boulevard Streetscape Project, Section 13-00256-00-PV, in an Amount Not to Exceed $143,500

End
Overview
Overview
In compliance with IDOT regulations, this change order is to pay for additional costs for expanding the sidewalk area to allow for additional outdoor dining, adjustments to layout and quantities of underground water and sewer work to account for unanticipated items, and costs for utility relocations on Harlem Avenue to coordinate with the Lincoln Development have increased the construction costs by approximately $103,633 to date. The sidewalk expansion work was previously approved by the Board and the utility relocation work is scheduled to start this month and is the Village's cost responsibility per the RDA with Lincoln Properties. The project is still ongoing and additional change orders will be needed for increased costs associated with project cost increases due to delays for coordination with the Lincoln Development.

Body
Staff Recommendation
Approve the Resolution.

Fiscal Impact
The FY2018 budget includes $715,000 in the Capital Improvement Fund, Public Works-Engineering, Streetscape Improvements, for the South Boulevard Streetscape project, account no. 3095-43780-101-5709595 which provides $143,537 for this current change order.

Background
In 2015 the Village of Oak Park entered into a Local Agency Agreement with the State of Illinois for the South Boulevard Streetscape project. Construction on the project started in 2016 which focused on completing the underground water and sewer improvements, temporary traffic signals, streetscaping on the north side of the street along the viaduct, and streetscaping in front of the existing businesses from the alley to Marion Street. Construction on the project was then suspended to allow for the construction of the Lincoln Developme...