Regular Village Board meetings are typically held at 7:00 p.m., the first three Tuesdays of each month in Council Chambers of Village Hall (room 201), 123 Madison St. When a Regular Meeting falls on a holiday, the meeting typically is held the following night. The Village Board also meets in special sessions from time to time. However, dates and times of Special Meetings can vary and may change.

File #: RES 18-940    Name:
Type: Resolution Status: Passed
In control: President and Board of Trustees
On agenda: 7/30/2018 Final action: 7/30/2018
Title: A Resolution Authorizing the Submission of a Metropolitan Water Reclamation District of Greater Chicago Green Infrastructure Program Partnership Funding Opportunity Application for a Green Alley Improvements Project
Attachments: 1. 7-23-18_Resolution-MWRD_GreenGrant_Alleys.pdf, 2. 2019 Green Alley.pdf
Submitted By
Bill McKenna, Village Engineer

Reviewed By
LKS

Agenda Item Title
Title
A Resolution Authorizing the Submission of a Metropolitan Water Reclamation District of Greater Chicago Green Infrastructure Program Partnership Funding Opportunity Application for a Green Alley Improvements Project

End
Overview
Overview
This resolution authorizes staff to submit an application for a Green Alley Improvements project to the Metropolitan Water Reclamation District of Greater Chicago (MWRD) for their Green Infrastructure Program which is a cost sharing grant program.

Body
Staff Recommendation
Approve the Resolution.

Fiscal Impact
The FY2019 budget is proposed to include $2,700,000 in the Capital Improvement Fund, Public Works - Engineering, for Alley Improvements account no. 3095-43780-101-570964. Additional design costs to be paid by the Village will be necessary if Oak Park is selected for the program as design of green infrastructure is currently not included for 2019.

The MWRD cost sharing program does not have a predefined local match cost sharing percentage requirement or maximum or minimum levels of funding. Final cost sharing amounts will be determined after MWRD selects grant recipients. Based on staff's understanding of typical projects which have received similar MWRD funding in the past, staff is estimating that should the Village receive the grant that MWRD may fund the project at a 30/70 cost sharing split. The estimated construction costs for five green alleys is $950,000 for roughly $285,000 in MWRD funding and $665,000 in Village funds depending on final costs of the project once design is completed. Sharing the costs at this funding level would cost the Village about the same as a locally funded traditionally constructed concrete alley.

Background
The Metropolitan Water Reclamation District of Greater Chicago (MWRD) encourages and supports implementing green infrastructure (GI). GI is a range of engineered installations that stor...