Regular Village Board meetings are typically held at 7:00 p.m., the first three Tuesdays of each month in Council Chambers of Village Hall (room 201), 123 Madison St. When a Regular Meeting falls on a holiday, the meeting typically is held the following night. The Village Board also meets in special sessions from time to time. However, dates and times of Special Meetings can vary and may change.

File #: RES 18-1036    Name:
Type: Resolution Status: Passed
In control: President and Board of Trustees
On agenda: 11/12/2018 Final action: 11/12/2018
Title: A Resolution Approving an Amendment to an Independent Contractor Agreement with Stenstrom Petroleum Services, Inc. for Replacement of Underground Storage Tank Access Ports and Leak Detector Monitoring System for the Fuel Storage Tanks at the Public Works Center Due to a Change Order in a New Amount not to Exceed $47,357.00 and Authorizing its Execution
Attachments: 1. Resolution-UST Change Order, 2. Amendment-UST Change Order, 3. Attachment-UST Change Order, 4. Attachment-Oak Park change order #1 invoice, 5. Attachment-Oak Park invoice-final

Submitted By                     

John P. Wielebnicki, Public Works Director

 

Reviewed By

CLP

 

Agenda Item Title

Title

A Resolution Approving an Amendment to an Independent Contractor Agreement with Stenstrom Petroleum Services, Inc. for Replacement of Underground Storage Tank Access Ports and Leak Detector Monitoring System for the Fuel Storage Tanks at the Public Works Center Due to a Change Order in a New Amount not to Exceed $47,357.00 and Authorizing its Execution

 

End

Overview

Overview

In order to complete the repair work to the Underground Storage Tank (UST) leak detector monitoring system and sensors, additional repairs to buried deteriorated conduit and junction boxes were added to the original scope.  The change order increases the contract by $4,672 from the previously approved $42,685 to $47,357.

 

Body

Staff Recommendation

Approve the Resolution.

 

Fiscal Impact

The FY2018 Capital Building Improvements Budget provides for a total of $60,000.00 for the above projects.  The proposed change order is within the budgeted amount.

 

The Village Board previously approved an agreement with Stenstrom Petroleum Services, Inc. for replacement of the underground storage tank access ports and leak detector monitoring system in an amount not to exceed $44,819.00, which included the base bid of $42,685.00 plus a five percent (5%) contingency).

 

Background

In June 2018, the Village approved a Contract with Stenstrom Petroleum Services, Inc. for the replacement of the underground storage tank access ports and the leak detector monitoring system for the fuel storage tanks located at the Public Works Center. Work was underway on this project and due to unanticipated conditions of buried deteriorated electrical conduit and junction boxes for the underground sensors, a change order was required in order for this project to be completed.

 

The existing conduit has rotten away leaving the wiring exposed.  This condition allowed the system to continue to function; hiding the fact the protective conduit was compromised.  This change order is for $4,672.00 to remove and replace the deteriorated conduit, junction boxes and associated wiring.

 

The original design of the project did not include conduit and junction box replacement as the system was functional. It was impossible to inspect condition of conduit as it is buried under concrete driveway.

 

This additional scope of work was authorized through the Departments Emergency Work Authorization procedure during construction since the work was required and so that the work could proceed and be completed allowing the Village fuel island to be placed back into service in a timely manner.

 

Alternatives

The Board can delay action to gain additional information.

 

Previous Board Action

On June 18, 2018, the Village Board approved an agreement with Stenstrom Petroleum Services, Inc.

 

Citizen Advisory Commission Action

N/A.

 

Anticipated Future Actions/Commitments

None at this time.

 

Intergovernmental Cooperation Opportunities

The Village fuel system is used by all Village Departments as well as the Park District, School District 97, School District 200 and the Library.

 

Performance Management (MAP) Alignment

This work is in alignment with the Governance Priority for the Public Works Department for Infrastructure/Capital Programs.