Regular Village Board meetings are typically held at 7:00 p.m., the first three Tuesdays of each month in Council Chambers of Village Hall (room 201), 123 Madison St. When a Regular Meeting falls on a holiday, the meeting typically is held the following night. The Village Board also meets in special sessions from time to time. However, dates and times of Special Meetings can vary and may change.

File #: RES 19-191    Name:
Type: Resolution Status: Passed
In control: President and Board of Trustees
On agenda: 6/17/2019 Final action: 6/17/2019
Title: A Resolution Approving a Change Order for the Contract with Cerniglia Co. for Project 18-1, Water and Sewer Main Improvements, and a Second Amendment to the Contract for an Additional Amount Not to Exceed $235,000 and Authorizing its Execution
Attachments: 1. Resolution_18-1 Water and Sewer Change Order, 2. Amendment2_Cerniglia_18-1ChangeOrder_6-17-19, 3. 18-1Cerniglia_OriginalContract, 4. Amendment1_18-1Cerniglia_12-10-18

Submitted By                     

Bill McKenna, Village Engineer

 

Reviewed By

LKS

 

Agenda Item Title

Title

A Resolution Approving a Change Order for the Contract with Cerniglia Co. for Project 18-1, Water and Sewer Main Improvements, and a Second Amendment to the Contract for an Additional Amount Not to Exceed $235,000 and Authorizing its Execution

 

End

Overview

Overview

Due to unforeseen conditions for the water and sewer construction project this change order will result in the final contract value being over the awarded amount.  These items generally include replacing defective large diameter water main valves and for project delays as a result of the defective valves.  Work for replacing the valves is scheduled for late June pending approval of the change order.  These various changes total approximately $235,000 and adjust the previously approved contract amount of $2,377,689 to $2,612,689.

 

End

Recommendation

Recommendation

Approve the Resolution

 

Body

Staff Recommendation

Approve the Resolution

 

Fiscal Impact

There are available funds for this change order in the Water & Sewer Fund, Public Works - Water, Water Distribution, Capital Improvements account no. 5040-43730-777-570707 which includes $100,000 for Water Valve Replacement and from the Water & Sewer Fund, Public Works - Sewer, Sewer Collection, Capital Improvements account no. 5040-43750-781-570707 which has  $415,459 available for Sewer Improvements/Flood Mitigation to fund this change order.

 

Background

The change order is needed due to the need to replace existing broken water valves which were discovered during the water main project on Berkshire Street from Grove Avenue to Linden Avenue.  These broken water valves, primarily on the Village’s 14” water main on Berkshire are from 1981, prevented the completion of this project as the Village cannot shut off the water on this water main to allow work to progress. 

 

Numerous days of lost productivity were encountered as the Village tried unsuccessfully to shut off water to allow for the construction project to progress.  Ultimately, staff directed the contractor to purchase and install replacement valves on the 14” water main.  Work for replacing these water valves is scheduled to occur in late June of this year pending approval of this change order.

 

These valves are needed in order complete the water main improvement project on Berkshire and more importantly in order to maintain the Village’s water distribution system in the north-central part of the Village as we currently cannot turn off water to many of the residential blocks in this part of the Village should any water main breaks occur until these broken valves are replaced.  Work by the Public Work’s Water and Sewer Division and the Engineering Division to determine the locations of broken valves and determine appropriate solutions resulted in losing the entire spring construction season for this project.   

 

The change order will include costs associated with days the contractor was on-site trying to complete work and the Village could not shut the water off due to broken valves; assistance by the contractor in digging up and finding broken valves and piping; costs for the future purchase and installation of replacement water valves; and for increases in labor rates starting in June of 2019 as the entire project, including work on Clarence Avenue from Roosevelt Road to Harvard, was intended to be completed by June of 2019 per the original contract prior to labor rate increases.

 

Alternatives

The alternative to this recommendation could be to delay action to gain additional information.

 

Previous Board Action

On September 17, 2018, the Village Board approved a contract with Cerniglia Co. for Project 18-1, Water and Sewer Main Improvements, in an Amount not to exceed $2,277,689

 

On December 10, 2018 the Village Board approved a Change Order for the Contract with Cerniglia Co. for Project 18-1, Water and Sewer Main Improvements, and an Amendment to the Contract for an Additional Amount Not to Exceed $100,000

 

Citizen Advisory Commission Action

N/A.

 

Anticipated Future Actions/Commitments

None at this time.

 

Intergovernmental Cooperation Opportunities

None at this time.