Regular Village Board meetings are typically held at 7:00 p.m., the first three Tuesdays of each month in Council Chambers of Village Hall (room 201), 123 Madison St. When a Regular Meeting falls on a holiday, the meeting typically is held the following night. The Village Board also meets in special sessions from time to time. However, dates and times of Special Meetings can vary and may change.

File #: RES 19-240    Name:
Type: Resolution Status: Passed
In control: President and Board of Trustees
On agenda: 9/16/2019 Final action: 9/16/2019
Title: A Resolution Authorizing the Rejection of All Bids for Project 19-16, Lake and Forest Sidewalk Planter as Reviewed at the September 9, 2019 Special Meeting
Attachments: 1. Resolution_19-16 Lake Forest Sidewalk Planter, 2. RenderingandPlans_LakeForestPlanter, 3. Proposal_19-16LakeForestPlanter_MYS, 4. Bid Summary 19-16 Lake Forest Planter

Submitted By                     

Bill McKenna, Village Engineer

 

Reviewed By

LKS

 

Agenda Item Title

Title

A Resolution Authorizing the Rejection of All Bids for Project 19-16, Lake and Forest Sidewalk Planter as Reviewed at the September 9, 2019 Special Meeting

 

End

Overview

Overview

The Village received one bid on June 20, 2019 in an amount of $204,500 for Project 19-16, Lake and Forest Granite Planter Installation.  The project includes installing a granite curbed planter feature with bronze lettering and decorative lighting on Lake Street at Forest Avenue.  In order to save money staff recommends rejecting the one bid and constructing the granite planter as designed with the 2020 Lake Street streetscape project.  For more information about this item and Village Board discussion, please review the agenda materials for the September 9, 2019 special meeting.

   

 

End

Recommendation

Recommendation

Approve the Resolution

 

Body

Fiscal Impact

The recommended FY2020 Budget includes $7,162,022 of funds in the Capital Improvement Fund, Public Works - Engineering, Streetscaping, for the Lake Street Streetscape Project which will be used to fund this work. 

 

Background

Competitive bids were opened on June 20, 2019, for Project 19-16, Lake and Forest Sidewalk Planter Installation.  The Village received one bid for this project from MYS, Incorporated in an amount of $204,500.  The project includes installing a granite curbed planter feature with bronze lettering and decorative lighting on Lake Street at Forest to coordinate work with the Albion and Vantage developments’ streetscape and minimize future disruption with the 2020 Lake Street streetscape project at this location. 

 

Based on direction from the Village Board at the July 8, 2019 regular meeting staff reached out to other potential funding partners for this work such as DTOP and the Albion Development and were not able to get commitments to help fund this work. 

 

As discussed at the September 9, 2029 special meeting, staff recommended that in order to reduce costs for the installation of the granite planter, the Village should reject the bid for this project and construct the granite planter as part of the Lake Street Streetscape Project in 2020.  This option will provide the greatest cost reduction by essentially eliminating the costs for traffic control, mobilization, and reduce the costs of other individual items due to economy of scale.  Cost savings may be in the order of $60,000 to $80,000 by deferring the work.

 

The design of the planter is in keeping with the February 26, 2018 regular meeting in which the Village Board approved the Lake Street Improvement Project’s scope, including the projects’ limits, decorative materials, and specialty features.  The granite curbed planter includes bronze lettering reading “Downtown Oak Park” and will include decorative pedestrian lighting and an in-ground LED lighting to illuminate the Downtown Oak Park lettering.   Plans and a rendering of the planter are attached.

 

Alternatives

The alternative to this recommendation could be to delay action to gain additional information. 

 

Previous Board Action

At the September 9, 2019 special meeting the Village Board concurred with staff’s recommendation to reject the bid for Project 19-16, Lake and Forest Sidewalk Planter and to construct the planter as currently designed with the Lake Street Streetscape project in 2020.

 

At the July 8, 2019 regular meeting the Village Board had a discussion and a presentation regarding the business district coordination and website development for the upcoming Lake Street Improvement projects.

 

At the May 20, 2019 regular meeting the Village Board approved a Contract with Electric Conduit Construction Co. for Project 19-13, Lake Street and Forest Avenue Traffic Signal Improvements in an amount not to exceed $426,660.

 

At the November 19, 2018 regular meeting the Village Board approved a Resolution Authorizing Temporary Construction Easements and Permanent Sidewalk Easements on Lake Street for the Lake Street Streetscape Project, Section 16-00264-00-PV. 

 

At the November 5, 2018 regular meeting the Village Board approved a Resolution Authorizing Local Funding and a Local Public Agency Agreement for Federal Participation with the State Of Illinois for Construction of the Lake Street Streetscape Project, Section 16-00264-00-PV. 

 

At the November 5, 2018 regular meeting the Village Board approved a Professional Services Agreement with TranSystems Corporation for Phase III Construction Engineering for the Lake Street Improvement Projects in an amount not to exceed $1,464,930.   

 

At the November 5, 2018 regular meeting the Village Board approved a Resolution Approving a Contract with Trine Construction Corp. for Project 19-1, Lake Street Sewer and Water Main Improvements, in an amount not to exceed $1,862,000.

 

At the September 4, 2018 regular meeting the Village Board Approved a Highways Land Acquisition Contract for Negotiation services with Swanson and Brown, Ltd. for Right-of-Way Acquisition for the Lake Street Improvement Project in an amount not to exceed $103,900.

 

At the July 9, 2018 regular meeting the Village Board Approved a Third Amendment to the Professional Services Agreement with Thomas Engineering Group LLC for the Design of the Lake Street Streetscape, Resurfacing, and Utility Improvement Projects to include Coordination with Developments and Revisions to Projects’ Scope for an additional $179,440.

 

At the March 5, 2018 regular meeting the Village Board approved the Lake Street Improvement projects’ scope and limits and provided direction to staff to modify the limits and scope to reduce the overall budget for construction of the projects to $15 million.

 

At the March 5, 2018 regular meeting the Village Board Approved a Second Amendment to the Professional Services Agreement with Thomas Engineering Group LLC for the Design of the Lake Street Streetscape, Resurfacing, and Utility Improvement Projects to include Design Modifications to existing Sidewalk Vaults for an additional $80,648.

 

At the March 5, 2018 regular meeting the Village Board Approved an Agreement with Tetra Tech, Inc., for an Environmental Preliminary Site Investigation for the Lake Street Improvement Projects in an amount not to exceed $36,511.

 

At the February 26, 2018 regular meeting the Village Board Approved the Lake Street Improvement Project’s Scope, Including the Projects’ Limits, Decorative Materials, and Specialty Features with a budgeted amount of $15 million.

 

At the October 16, 2017 regular meeting the Village Board approved a Professional Services Agreement with The Lakota Group, Inc., for Phase 2 Professional Landscape Architecture and Planning Services for the Lake Street Streetscape Project in an amount not to exceed $131,370.

 

At the January 17, 2017 regular meeting the Village Board Approved an Amendment to the Professional Services Agreement with The Lakota Group, Inc., for Phase 1 Professional Landscape Architecture and Planning Services for the Lake Street Streetscape Project for an additional $24,780

 

At the January 17, 2017 regular meeting the Village Board Approved an Amendment to the Professional Services Agreement with Thomas Engineering Group, LLC., for Professional Engineering Services for the design of the Lake Street Streetscape, Resurfacing, and Utility Improvement Projects for an additional $117,560.

 

On October 4, 2016, the Village Board authorized an agreement with The Lakota Group, Inc., for Phase 1 Professional Landscape Architecture and Planning Services for the Lake Street Streetscape Project in an amount not to exceed $99,000.

 

On August 1, 2016, the Village Board authorized an agreement with Thomas Engineering Group, LLC., for Professional Engineering Services for the design of the Lake Street Streetscape, Resurfacing, and Utility Improvement Projects in an amount not to exceed $1,080,000. 

 

At the July 18, 2016 regular meeting the Village Board approved a Resolution Authorizing the Submission of a 2016 Federal Surface Transportation Program Grant Application for the Lake Street Streetscape and Resurfacing Project.

 

At the June 6, 2016 regular meeting the Village Board approved a Resolution Authorizing the Submission of a 2016 Illinois Transportation Enhancement Program (ITEP) Grant Application for the Lake Street Streetscape Project.

 

At the June 6, 2016 regular meeting the Village Board approved a Resolution Requesting the Illinois Department of Transportation Repurpose Federal Funds Earmarked for the I-290 Cap the Ike Projects, IL456 and IL478, to the proposed Lake Street Resurfacing and Streetscape Project according to the Consolidate Appropriations Act, 2016.

 

On February 8, 2016 the Village Board was given a presentation related to Construction, Parking and Mobility Services along the Lake Street Corridor from Harlem to Austin and directed staff to Request Proposals for the Preliminary and Design Engineering of the Lake Street Streetscape and Resurfacing Project.

 

On November 2, 2015 the Village Board was given a presentation on the Lake Street Streetscape Enhancement project which included a recommended project scope and material selections based on Board comments. 

 

On May 11, 2015 the Village Board was given a presentation on the Lake Street Streetscape Enhancement project.

 

On August 20, 2014 the Disability Access Commission met at their regular open public meeting to review the proposed streetscape project and provided comments.

 

On January 7, 2013 Lakota Group and staff presented the recommendations of the Streetscape Committee for the Lake Street Streetscape project to the Village Board which included four options for scope and materials.   The results of the surveys and walking tours were also presented.

 

On June 4, 2012 the Village Board the Village Board directed staff to form the Downtown District Streetscape Committee who would help in the development of various streetscape scenarios for Board consideration.

 

On March 15, 2012 the Village Board authorized an agreement with Lakota Group for design services related to the Lake Street Corridor from Harlem Ave to Euclid Ave.

 

Citizen Advisory Commission Action

N/A.

 

Anticipated Future Actions/Commitments

None at this time.

 

Intergovernmental Cooperation Opportunities

None at this time.