Regular Village Board meetings are typically held at 7:00 p.m., the first three Tuesdays of each month in Council Chambers of Village Hall (room 201), 123 Madison St. When a Regular Meeting falls on a holiday, the meeting typically is held the following night. The Village Board also meets in special sessions from time to time. However, dates and times of Special Meetings can vary and may change.

File #: RES 19-335    Name:
Type: Resolution Status: Passed
In control: President and Board of Trustees
On agenda: 11/18/2019 Final action: 11/18/2019
Title: A Resolution Approving an Independent Contractor Agreement with Sewertech LLC for Project 19-10 Sewer Cleaning and Inspection, in an Amount not to Exceed $53,680 and Authorizing its Execution.
Attachments: 1. Resolution_19-10SewerCleaning.pdf, 2. 11-18-19_Attachment A_IndependentContract_19-10_SewerTech.pdf, 3. 11-18-19_AttachmentB_19-10Bid Summary.pdf, 4. 11-18-10_AttachmentC_19-10_LocationMap.pdf, 5. 11-18-19_AttachmentD_19-10_SewerTech_Proposal.pdf, 6. Corporation_LLC Search_Certificate of Good Standing.pdf

Submitted By                     

Bill McKenna, Village Engineer

 

Reviewed By

LKS

 

Agenda Item Title

Title

A Resolution Approving an Independent Contractor Agreement with Sewertech LLC for Project 19-10 Sewer Cleaning and Inspection, in an Amount not to Exceed $53,680 and Authorizing its Execution.

 

End

Overview

Overview

Competitive proposals were received on October 31st for the Sewer Cleaning and Inspection Project.  Three contractors submitted proposals for the project. The lowest qualified proposal was submitted by Sewertech LLC in the amount of $53,679.70.

 

End

Recommendation

Recommendation

Approve the Resolution

 

Fiscal Impact

The costs for this project are included in the FY2019 budget in the Water and Sewer Fund, Public Works-Sewer, Sewer Collection, External Support, account #5040-43750-781-530667 which provides $100,000 for the Annual Sewer Televising and cleaning project.  

 

Background

The project consists of cleaning and television inspection of approximately 2.8  miles of sewers ranging in size from 9-inches to 2.5-feet diameter and approximately 1.05 miles of sewers larger than 2.5-feet diameter.  Sewer cleaning and inspection is an annual project which is used to determine sewer condition, future capital improvement needs, and to help manage the sewer system asset.  The locations of the sewers scheduled for sewer cleaning and inspection are included as an attachment.

 

Alternatives

The alternative to this recommendation could be to delay action to gain additional information.

 

Previous Board Action

N/A.

 

Citizen Advisory Commission Action

N/A.

 

Anticipated Future Actions/Commitments

None at this time.

 