Regular Village Board meetings are typically held at 7:00 p.m., the first three Tuesdays of each month in Council Chambers of Village Hall (room 201), 123 Madison St. When a Regular Meeting falls on a holiday, the meeting typically is held the following night. The Village Board also meets in special sessions from time to time. However, dates and times of Special Meetings can vary and may change.

File #: RES 20-058    Name:
Type: Resolution Status: Passed
In control: President and Board of Trustees
On agenda: 2/3/2020 Final action: 2/3/2020
Title: A Resolution Authorizing the Submission of a Metropolitan Water Reclamation District of Greater Chicago Stormwater Partnership Program Application for the Lemoyne Street Sewer Project
Attachments: 1. Resolution_MWRD Stormwater Grant Application Lemoyne, 2. Lemoyne St - Sewer Master Plan Report Pages
Submitted By
Bill McKenna, Village Engineer

Reviewed By
LKS

Agenda Item Title
Title
A Resolution Authorizing the Submission of a Metropolitan Water Reclamation District of Greater Chicago Stormwater Partnership Program Application for the Lemoyne Street Sewer Project

End
Overview
Overview
This resolution authorizes staff to submit an application to the Metropolitan Water Reclamation District of Greater Chicago (MWRD) for their Stormwater Partnership Program which is a cost sharing grant program for a proposed flood mitigation project on Lemoyne Street from East Avenue to Edmer Avenue. The Lemoyne Sewer Project is already included in the FY2020 budget and any grant funds received would offset local water and sewer funds.

End
Recommendation
Recommendation
Approve the Resolution

Fiscal Impact
The FY2020 Budget includes $1,500,000 in funds in the Water and Sewer Fund, Public Works - Sewer, Sewer Collection, Capital Improvements account no. 5040-43750-781-570707 for the Lemoyne Street Flood Mitigation Project.

The MWRD cost sharing program does not have a predefined local match cost sharing percentage requirement or maximum or minimum levels of funding. Final cost sharing amounts will be determined after MWRD selects receipts of their grants. Based on staff's understanding of typical projects which have received similar MWRD funding in the past, staff is estimating that should the Village receive the grant that MWRD may fund the project at a 50/50 cost sharing split for roughly $750,000 in MWRD funding and $750,000 in Village funds depending on final costs of the project once design is completed.

Should the Village be awarded the cost sharing grant, construction of the project will need to be deferred until 2021 in order to allow for time to complete an IGA with MWRD for the grant.

Background
The Village's Combined Sewer System Master Plan Report identifies a number of larger relief sewer projects to improve the performance of the Village's c...