Regular Village Board meetings are typically held at 7:00 p.m., the first three Tuesdays of each month in Council Chambers of Village Hall (room 201), 123 Madison St. When a Regular Meeting falls on a holiday, the meeting typically is held the following night. The Village Board also meets in special sessions from time to time. However, dates and times of Special Meetings can vary and may change.

File #: ORD 20-022    Name:
Type: Ordinance Status: Passed
In control: President and Board of Trustees
On agenda: 6/1/2020 Final action: 6/1/2020
Title: An Ordinance Granting an Extension of Time to Complete Construction of the Planned Development at 715-717 South Boulevard (Residences of South Boulevard) and Waiving and Suspending the Right-of-way Obstruction Permit Fee and Parking Meter Obstruction Fee for the Planned Development
Attachments: 1. Ordinance, 2. Letter w/ Attachments, 3. ORD 17-174 Planned Development, 4. ORD 18-398 Extension for Start, 5. ORD 19-49 Fee Waiver
Submitted By
Tammie Grossman, Director, Development Customer Services

Reviewed By
LKS

Agenda Item Title
Title
An Ordinance Granting an Extension of Time to Complete Construction of the Planned Development at 715-717 South Boulevard (Residences of South Boulevard) and Waiving and Suspending the Right-of-way Obstruction Permit Fee and Parking Meter Obstruction Fee for the Planned Development

End
Overview
Overview
717 South Boulevard, LLC is requesting approval of an extension of its planned development ordinance deadline to allow additional time to finish construction of the multi-unit residential condominium building constructed at 715-717 South Boulevard. In addition, the developer seeks an extension of the waiver and a suspension of the right-of-way and parking meter obstruction fees adjacent to the development site. This is its second request for these items.

End
Recommendation
Recommendation
Approve the Ordinance to allow an extension of time for the completion of construction for an additional twelve (12) months from March 6, 2020 to March 6, 2021 and waive the construction fees for the right of way and parking from January 1, 2020 through the end of construction.

Fiscal Impact
The Village will not collect the fees associated with an obstruction permit and parking meter fees due to the planned development ordinance requirement that all construction staging and traffic occur along the South Boulevard parking area adjacent the development site. This waiver and suspension was approved by the Village Boare for the previous year 2019.

Background
Article 14; Section 14.5(G)2&3 of the Zoning Code provides that an approval of a planned development permit by the Board of Trustees shall be null and void if the recipient does not file an application for a building permit for the proposed development within nine months after the date of adoption of the Zoning Ordinance approving the development permit; commence construction within eighteen (18) months...