Regular Village Board meetings are typically held at 7:00 p.m., the first three Tuesdays of each month in Council Chambers of Village Hall (room 201), 123 Madison St. When a Regular Meeting falls on a holiday, the meeting typically is held the following night. The Village Board also meets in special sessions from time to time. However, dates and times of Special Meetings can vary and may change.

File #: RES 20-198    Name:
Type: Resolution Status: Passed
In control: President and Board of Trustees
On agenda: 9/8/2020 Final action: 9/8/2020
Title: A Resolution Approving a Second Amendment to a Contract with Trine Construction Corp. for Project 19-1, Lake Street Sewer and Water Main Improvements, to Change the Not To Exceed Amount from $2,190,623 to $2,292,623 and Authorizing its Execution
Attachments: 1. Resolution Change Order Lake St W&S, 2. Amendment2_Contract_Trine_LakeSt W&S_ChangeOrder, 3. Contract and Amendment Lake St WaterSewer
Submitted By
Bill McKenna, Village Engineer

Reviewed By
LKS

Agenda Item Title
Title
A Resolution Approving a Second Amendment to a Contract with Trine Construction Corp. for Project 19-1, Lake Street Sewer and Water Main Improvements, to Change the Not To Exceed Amount from $2,190,623 to $2,292,623 and Authorizing its Execution

End
Overview
Overview
Various unanticipated underground utility conflicts, increased costs for contaminated soil disposal, additional work to replace broken valves, and unknown sewer conditions added additional cost above the approved contract amount for the Lake Street Sewer and Water Main Improvements project. These changes total approximately $102,000 and adjust the previously approved contract amount of $2,190,623 to $2,292,623.

End
Recommendation
Recommendation
Approve the Resolution

Fiscal Impact
There are available funds in the FY2020 Budget for this change order in the Water and Sewer Fund, with the Water and Sewer Fund, Public Works - Sewer, Sewer Collection, Capital Improvements, for sewer main replacement, account no. 5040-43750-781-570707 providing $102,000 for this change order from cost savings from deferred projects.

Background
During construction various additional quantities of items resulted in an overall increase to the project's costs. There were additional quantities for removal and disposal of contaminated soils, additional water valves were needed to isolate existing broken water valves, changes due to unknown utility conflicts, additional sewer repair work in the lining section which increased the construction costs for the project by $102,000, or roughly 4.6%.

Alternatives
The alternative to this recommendation could be to delay action to gain additional information.

Previous Board Action
At the March 2, 2020 Village Board meeting, the Village Board approved an Amendment with Trine Construction Corp. for Project 19-1, Lake Street Sewer and Water Main Improvements, to Change the Not To Excee...