Regular Village Board meetings are typically held at 7:00 p.m., the first three Tuesdays of each month in Council Chambers of Village Hall (room 201), 123 Madison St. When a Regular Meeting falls on a holiday, the meeting typically is held the following night. The Village Board also meets in special sessions from time to time. However, dates and times of Special Meetings can vary and may change.

File #: RES 20-208    Name:
Type: Resolution Status: Passed
In control: President and Board of Trustees
On agenda: 9/21/2020 Final action: 9/21/2020
Title: A Resolution Approving a Contract with Schroeder Asphalt Services, Inc. for Project 20-2 Resurfacing of Various Streets, in an Amount not to Exceed $571,345 and Authorizing its Execution.
Attachments: 1. Resolution_20-2_Resurfacing.pdf, 2. 9-21-20_AttachmentA_Contract_Resurfacing.pdf, 3. 09-21-20_AttachmentB_Resurfacing_Bidsummary.pdf, 4. 09-21-20_AttachmentC_Resurfacing_LocationMap.pdf, 5. 09-21-20_AttachmentD_Resurfacing_Proposal.pdf, 6. Corporation_LLC Search_Certificate of Good Standing.pdf
Submitted By
Bill McKenna, Village Engineer

Reviewed By
LKS

Agenda Item Title
Title
A Resolution Approving a Contract with Schroeder Asphalt Services, Inc. for Project 20-2 Resurfacing of Various Streets, in an Amount not to Exceed $571,345 and Authorizing its Execution.

End
Overview
Overview
Competitive bids were opened on September 3, 2020, for the 20-2 Resurfacing of Various Streets project. Six contractors picked up bid documents and three bids were received. The low responsible bid was submitted by Schroeder Asphalt Services, Inc. in an amount of $571,344.50.

End
Recommendation
Recommendation
Approve the Resolution

Fiscal Impact
The FY2020 Budget includes $490,221 for the local street resurfacing and the Austin Boulevard resurfacing in the Capital Improvement Fund, Public Works - Engineering, Local Street Construction and $105,000 in the CDBG Fund for Development Customer Services - Neighborhood Services, Capital Improvements account no. 2083-46201-668-583652 to fund this project.

Background
This project includes 6 resurfacing blocks on 3 different streets, patching 20 blocks on 12 different streets, and upgrading various corners through the village to be in compliance with ADA requirements using CDBG funds.

The project includes the resurfacing of the Village's side of Austin Boulevard from Lake Street to just north of Chicago Avenue. The resurfacing of Austin was originally planned to be completed by the City of Chicago at the Village's cost per the Intergovernmental Agreement from July 2019 following the Village's water main improvement project on Austin Boulevard. Due to the COVID-19 pandemic, the Village delayed work on the water main project this spring due to its potential impacts to the water supply to the West Suburban Medical Center. The City of Chicago was unable to delay their work and proceeded with resurfacing their half of Austin this summer.

The Village's half of Austin Boulevard needs to be resurfaced based on its co...