Regular Village Board meetings are typically held at 7:00 p.m., the first three Tuesdays of each month in Council Chambers of Village Hall (room 201), 123 Madison St. When a Regular Meeting falls on a holiday, the meeting typically is held the following night. The Village Board also meets in special sessions from time to time. However, dates and times of Special Meetings can vary and may change.

File #: RES 22-3    Name:
Type: Resolution Status: Passed
In control: President and Board of Trustees
On agenda: 1/18/2022 Final action: 1/18/2022
Title: A Resolution Approving a Second Amendment to the Independent Contractor Agreement with JLJ Contracting, Inc. for the Construction of an Enclosure Adjacent to the Northeast Elevator/Stair Tower on the Second Level of the Village-Owned Oak Park River Forest High School Parking Structure to Change the Not-To-Exceed Amount From $76,400.00 to $80,050.00 and Authorizing Its Execution.
Attachments: 1. Resolution, 2. Second Amendment, 3. Change Order #2 - JLJ Contracting, 4. RES 21-294_JLJ Agreement
Submitted By
Tammie Grossman, Director, Development Customer Services

Reviewed By
AMZ

Agenda Item Title
Title
A Resolution Approving a Second Amendment to the Independent Contractor Agreement with JLJ Contracting, Inc. for the Construction of an Enclosure Adjacent to the Northeast Elevator/Stair Tower on the Second Level of the Village-Owned Oak Park River Forest High School Parking Structure to Change the Not-To-Exceed Amount From $76,400.00 to $80,050.00 and Authorizing Its Execution.

End
Overview
Overview
A second change order is needed for the agreement with JLJ Contracting, Inc. for the Elevator/Stair Tower Enclosure Project at the Oak Park River Forest High School Parking Structure due to additional costs to furnish and install two (2) custom metal pieces of flashing.

End
Recommendation
Recommendation
Approve the Resolution.

Fiscal Impact
A budget amendment providing for the additional $3,650.00 for this contract will be presented to the Village Board in the first quarter of 2022.

Background
The elevator on the second level of the OPRF High School parking structure is not adequately sheltered, with machinery and equipment exposed to inclement weather conditions throughout the year. This exposure contributes to numerous malfunctions, necessitating continual repairs to the elevator equipment. As part of the ongoing parking structure maintenance program outlined in the FY21 - 25 Capital Improvement Plan, an enclosure was proposed to be constructed adjacent to the northeast elevator/stair tower on the second level of the structure.
Design and construction management services for this project were estimated by staff to be less than $10,000.00. Pursuant to the Village's Purchasing Policy, staff requested bids from three (3) structural engineering firms. On March 23, 2021, the Village Manager executed a Professional Services Agreement with Walker Consultants, Inc. for design and construction management services in an amount not to exceed $8,600...

Click here for full text