Regular Village Board meetings are typically held at 7:00 p.m., the first three Tuesdays of each month in Council Chambers of Village Hall (room 201), 123 Madison St. When a Regular Meeting falls on a holiday, the meeting typically is held the following night. The Village Board also meets in special sessions from time to time. However, dates and times of Special Meetings can vary and may change.

File #: RES 23-195    Name:
Type: Resolution Status: Passed
In control: President and Board of Trustees
On agenda: 6/5/2023 Final action: 6/5/2023
Title: A Resolution Approving an Amendment to the Task Order for Design and Construction Management of the Public Works Wash Bay Improvement Project to Change the Not to Exceed Amount from $19,500 to $47,500 and Authorizing its Execution
Attachments: 1. Resolution - PW WashBay Amendment TranSystems.pdf, 2. Amendment TaskOrder PW WashBay DesignManagement - TranSystems.pdf, 3. PW Wash Bay Amendment Request Letter.pdf, 4. TaskOrder PublicWorks WashBay - Designand ConstructionManagement.pdf

Submitted By                     

Bill McKenna, Village Engineer

 

Reviewed By

A.M. Zayyad, Deputy Village Manager

 

Agenda Item Title

Title

A Resolution Approving an Amendment to the Task Order for Design and Construction Management of the Public Works Wash Bay Improvement Project to Change the Not to Exceed Amount from $19,500 to $47,500 and Authorizing its Execution

 

End

Overview

Overview

In 2022 the Village approved a Task Order with TranSystems Corporation for the design and construction management of the Public Work’s Wash Bay Improvement Project.  During the construction of the project differing site conditions were encountered primarily related to intermediate slab slopes and an existing waterproofing membrane that were not identified on the existing as-built plans for the building.  These new conditions required additional hours for redesigning the project and working with the contractor on solutions.  In addition to these changes during construction, TranSystems required additional hours beyond the original scope during the design due to changes in the building’s plumbing that were also not shown on the as-built plans.  All these changes amount to $28,000 and adjust the contract amount from $19,500 to $47,500.  There are available funds in the FY23 Budget to cover these additional costs.

 

End

Recommendation

Recommendation

Approve the Resolution.

 

Background

In 2022 the Village approved a Task Order with TranSystems Corporation for the design and construction management of the Public Work’s Wash Bay Improvement Project.  During the construction of the project differing site conditions were encountered primarily related to intermediate slab slopes and an existing waterproofing membrane that were not identified on the existing as-built plans for the building.  These unforeseen conditions required redesign for multiple issues for waterproofing, drainage, grading, and reviewing new materials and solutions proposed by the contractor.  In addition to these changes during construction, TranSystems required additional hours beyond the original scope during the design due to changes in the building’s plumbing that were also not shown on the as-built plans.  All these changes amount to $28,000 and adjust the contract amount from $19,500 to $47,500.  There are available funds in the FY23 Budget to cover these additional costs. 

 

Fiscal Impact

The FY23 Budget includes $2,500 for the construction management of the Public Works Wash Bay project in the Capital Building Improvement Fund, Department of Public Works - Building Maintenance, Building Maintenance account no. 3012-43790-101-540673.  There are available funds to cover the $28,000 needed for this Amendment in the Capital Improvement Fund, Public Works - Engineering, Project Engineering account no. 3095-43780-101-570706.

 

DEI Impact

N/A.

 

Alternatives

The alternative to this recommendation could be to delay action to gain additional information.

 

Previous Board Action

On February 6, 2023, the Village Board approved an Independent Contractor Agreement with D Kersey Construction Co. for the Public Works Center Wash Bay Drainage Improvements Project in an amount not to exceed $141,120. 

 

Citizen Advisory Commission Action

N/A.

 

Anticipated Future Actions/Commitments

None at this time.

 

Intergovernmental Cooperation Opportunities

None at this time.