A Resolution Confirming the Appointment of Members of the Bridging
the Ike Planning and Environmental Linkage Study Steering Committee
J.
Overview:
The Village is currently working with AECOM on the planning and environmental
linkage (PEL) study for expanded bridge decking over I-290. This resolution
confirms the appointment of 6 members of the steering committee who had not
yet been named on the previous resolution from March 24, 2026, in which the
steering committee was established, and 5 members were confirmed. The
steering committee, consisting of 11 members in total, will review and give input
on the best locations for expanded bridge decks (caps) over I-290 within the
constraints identified by IDOT during their I-290 preliminary design work and the
best uses for any expanded bridge decks. The steering committee will make
recommendations to the Village Board for the purpose and need for these
potential caps. The steering committee is comprised of partner agencies,
members from various commissions, and stakeholders in the project area.
A Resolution Approving an Amendment to the Task Order for
Professional Engineering Services with Baxter & Woodman, Inc., for
Design and Construction Engineering for the North Pump Station
Emergency Generator Project 24-12 to Change the not to Exceed Amount
from $105,000 to $133,900 and Authorizing its Execution
K.
Overview:
In 2023, the Village contracted with Baxter & Woodman to do the engineering
design and construction management for the North Pump Station Emergency
Generator Project. Baxter & Woodman has had to perform additional
construction management beyond the originally anticipated duration of the
project due to delays by the contractor. The additional work for overseeing this
project amounts to $28,900 and adjusts the task order from $105,000 to
$133,900. These additional costs are being deducted from the money due to
the contractor as liquidated damages since the project is beyond its completion
date.
A Resolution Approving an Amendment to the Independent Contractor
Agreement with J. Graham, LLC. for the Viaduct Art Installation to Change
the not to Exceed Amount from $235,000 to $295,000 and Authorizing its
Execution
L.
Overview:
In 2024, the Village approved an agreement with Graham Carraway for the
fabrication, installation, and purchase of an art installation under the viaduct on
Oak Park Avenue as part of the streetscape project. Costs for materials and
fabrication have exceeded the originally agreed-upon amount. The increased
costs are a result of delays outside the artist's control, including deferring
construction of the streetscape project from 2025 to 2026 and the timelines
associated with getting the mural artwork approved by the Oak Park Area Arts
Commission. This amendment increases the contract by $60,000 and adjusts
the agreement amount from $235,000 to $295,000.