Regular Village Board meetings are typically held at 7:00 p.m., the first three Tuesdays of each month in Council Chambers of Village Hall (room 201), 123 Madison St. When a Regular Meeting falls on a holiday, the meeting typically is held the following night. The Village Board also meets in special sessions from time to time. However, dates and times of Special Meetings can vary and may change.

File #: ORD 23-29    Name:
Type: Ordinance Status: Passed
In control: President and Board of Trustees
On agenda: 5/15/2023 Final action: 5/15/2023
Title: An Ordinance Granting an Extension of Time to Complete Construction of the Planned Development at 715-717 South Boulevard (Residences of South Boulevard) to November 30, 2023
Attachments: 1. Ordinance, 2. Extension request, 3. ORD 22-53, 4. ORD 22-15, 5. ORD 21-28, 6. ORD 20-22, 7. ORD 18-398, 8. ORD 17-174- Residence of So. Blvd., 9. ORD 23-29(Final).pdf
Submitted By
Tammie Grossman, Development Customer Services Director

Reviewed By
A.M. Zayyad, Deputy Village Manager

Agenda Item Title
Title
An Ordinance Granting an Extension of Time to Complete Construction of the Planned Development at 715-717 South Boulevard (Residences of South Boulevard) to November 30, 2023

End
Overview
Overview
717 South Boulevard, LLC is requesting approval of an extension of its planned development ordinance deadline to allow additional time to finish construction of the multi-unit residential condominium building constructed at 715-717 South Boulevard. This is the sixth request to extend the development's timeline.

End
Recommendation
Recommendation
Approve the Ordinance to allow an extension of time for the completion of construction. The applicant is requesting an additional six (6) months from May 31, 2023, to November 30, 2023, as stated in the attached request letter. Staff would support the extension as the developer has contracted with a broker and is actively marketing the units.

Fiscal Impact
N/A.

Background
The Zoning Ordinance at the time of Planned Development approval stated in Article 14; Section 14.5(G) 2&3 that an approval of a planned development permit by the Board of Trustees shall be null and void if the recipient does not file an application for a building permit for the proposed development within nine months after the date of adoption of the Zoning Ordinance approving the development permit; commence construction within eighteen (18) months, and complete the project within thirty-six (36) months. Article 14 of the Zoning Ordinance allows the Village Board to grant an extension of time, provided the applicant shows good cause in writing.

The Applicant has indicated that additional time is necessary, as stated in the attached letter dated April 17, 2023, attached hereto. Ordinance Number 17-174, approved by the Village Board on March 6, 2017, authorized the construction of a multiple-unit res...