Regular Village Board meetings are typically held at 7:00 p.m., the first three Tuesdays of each month in Council Chambers of Village Hall (room 201), 123 Madison St. When a Regular Meeting falls on a holiday, the meeting typically is held the following night. The Village Board also meets in special sessions from time to time. However, dates and times of Special Meetings can vary and may change.

File #: RES 17-569    Name:
Type: Resolution Status: Passed
In control: President and Board of Trustees
On agenda: 8/7/2017 Final action: 8/7/2017
Title: A Resolution Approving an Independent Contractor Agreement for the Purchase and Installation of three (3) Dual Electric Vehicle Charging Stations for the Holley Court Garage and two (2) Dual Electric Vehicle Charging Stations for the Avenue Garage from CD, LLC, d/b/a Carbon Day Automotive in an Amount not to Exceed $46,000, Authorizing its Execution and Waiving the Village's Bid Process for Said Purchase and Installation
Attachments: 1. Electric Charging Stations Resolution, 2. 08.07.17 ICA Carbonday Automotive.pdf, 3. QUOTATION Oak Park Avenue Garage Installation.pdf, 4. Quotation Oak Park CT4027 Avenue Garage.pdf, 5. Quotation Oak Park CT4027 Holley Court - 2nd floor.pdf, 6. Quotation Oak Park CT4027 Holley Court - first floor.pdf, 7. QUOTATION Oak Park Holly Court Garage 1st floor Installation.pdf, 8. QUOTATION Oak Park Holly Court Garage 2nd floor Installation.pdf, 9. Oak Park - Holley Garage Report, 10. Oak Park - Avenue Garage Report
Submitted By
Tammie Grossman, Director Development Customer Services

Reviewed By
LKS

Agenda Item Title
Title
A Resolution Approving an Independent Contractor Agreement for the Purchase and Installation of three (3) Dual Electric Vehicle Charging Stations for the Holley Court Garage and two (2) Dual Electric Vehicle Charging Stations for the Avenue Garage from CD, LLC, d/b/a Carbon Day Automotive in an Amount not to Exceed $46,000, Authorizing its Execution and Waiving the Village's Bid Process for Said Purchase and Installation

End
Overview
Overview
Staff is recommending that the Village of Oak Park purchase from the existing provider Carbonday the updated version of the existing ChargePoint equipment for 3 new electric vehicle charging units at Holley Court and 2 new units at Avenue Garage. The new units feature a longer charging cable resolving issues users may have in reaching the charging cable to vehicles.

Body
Staff Recommendation
Approve the Resolution.

Fiscal Impact
The FY 2017 Parking and Mobility Services Capital Improvement Plan Budget provides $46,000 for electric vehicle charging stations account no. 5060-43770-784-570705 ($25,000.00) and account no. 5060-43770-788-570705 ($21,000.00).

The cost will not exceed $46,000.00 in total.

Currently, the Illinois Department of Commerce and Economic Opportunity (DCEO) does not have an active Electric Vehicle Infrastructure Rebate Program. However, in the past these rebate have typically been retroactive and covered 50% of Level II EV charging station equipment and installation costs up to the following caps: $3,750 per networked single station; $3,000 per non-networked single station; $7,500 per networked dual station; and $6,000 per non-networked dual.

Background
On November 19, 2012 the Village Board approved the installation of two (2) dual level 2 electric vehicle (EV) Charging Stations, one at Village-owned Avenue Garage, and one at Village-owned Holley Court, for the purpose of adding to...